Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP20-0179
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Complete (Recurring)
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued. No issues at this time. |
08/12/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by NGARCIA3 - Continued |
07/28/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by NGARCIA3 - Continued 520 N Houghton Rd, |
06/08/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued, unscheduled courtesy inspection. correction required. Track out noted, Track out protection needs corrected, schedule inspections biweekly as previously requested |
04/26/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by NGARCIA3 - Continued 520 N Houghton Rd |
04/15/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued |
02/24/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued Minor track out noted |
02/17/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued. Track out on Houghton Road. Material importing and utility work in progress |
01/28/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued. No issues at this time. |
01/04/2022 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Minor track out noted on Houghton Road. Track out rock covering only half of the driveway. |
12/16/2021 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by VVERA1 - Continued. Minor track out noted on Howton Road |
11/30/2021 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Met with Jay Knoll and Samuel on site. |
11/05/2021 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. No concerns at this time. Please schedule biweekly inspections |
05/10/2021 | SITE - Stormwater Follow-up | DROBERTS | Correction Required | Entered by VLEON1 - CORRECTIONS REQUIRED FOR 520 N HOUGHTON RD AT THIS TIME. THE CONTRACTOR WILL WORK ON INSTALLING CONTROLS FOR THIS SITE OVER THE NEXT WEEK ALONG THE WEST SIDE OF THE PROJECT IN THE NORTH WESTERN QUADRANT COR THE CONSTRUCTION OF A PRIVATE ACCESS ROAD FOR AN EXISTING STRUCTURE. |