Permit: DP20-0167

Parcel: 141431940


Addresses:

6601 E BENSON HY


Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Permit Number - DP20-0167

Inspection Description - ENGR Grading Final

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/14/2022 ENGR Grading Final DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED, MOST OF THE SITE WORK IS BEING WATCHED BY TDOT DUE TO THE PUBLIC ROADWAYS 6890 E CAMINO BOLEADORAS
10/14/2022 ENGR Grading Final DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED, MOST OF THE SITE WORK IS BEING WATCHED BY TDOT, HOUSES ARE BEING CONSTRUCTED AT THIS TIME ON THIS SITE. 6801 E BENSON HY
10/14/2022 ENGR Grading Final DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED, MOST OF THE SITE WORK IS BEING WATCHED BY TDOT, HOUSES ARE BEING CONSTRUCTED AT THIS TIME ON THIS SITE. 6601 E BENSON HY
09/30/2022 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED AT THIS TIME, MOST OF THE WORK ON THIS SITE IS VERTICAL FOR THE INDIVIDUAL LOTS
09/30/2022 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED AT THIS TIME, MOST OF THE WORK ON THIS SITE IS VERTICAL FOR THE INDIVIDUAL LOTS
09/30/2022 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED AT THIS TIME, MOST OF THE WORK ON THIS SITE IS VERTICAL FOR THE INDIVIDUAL LOTS
09/16/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - PARTIAL, CREWS WORKING ON GRADING AND UTILITY WORK 6801 E BENSON HY
09/16/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - IS PARTIAL, CREWS WORKING ON GRADING AND UTILITY WORK 6601 E BENSON HY
08/19/2022 ENGR Grading Final DROBERTS Continued Entered by VVERA1 - CONTINUE ON WORKING ON THE INSTALLATION OF UTILITIES AT VARIOS LOCATIONS THROUGHOUT THE SITE
08/05/2022 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - 6890 CONTINUED, CREWS ARE WORKING ON PREPARE CURB AND ROADWAY GRADES FOR FUTURE CONSTRUCTION.
08/05/2022 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED, CREWS ARE WORKING ON PREPARE CURB AND ROADWAY GRADES FOR FUTURE CONSTRUCTION.
08/05/2022 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED, CREWS ARE WORKING ON PREPARE CURB AND ROADWAY GRADES FOR FUTURE CONSTRUCTION.
05/13/2022 ENGR Grading Final DROBERTS Partial Approval Entered by VVERA1 - IS PARTIAL, CREWS WORKING ON NEEDED SITE WORK AS NEEDED FOR A FULL C OF O.
05/13/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - PARTIAL, CREWS WORKING ON NEEDED SITE WORK AS NEEDED FOR A FULL C OF O. 6801 E BENSON HY
05/13/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - PARTIAL, CREWS WORKING ON NEEDED SITE WORK AS NEEDED FOR A FULL C OF O. 6601 E BENSON HY
04/01/2022 ENGR Grading Final DROBERTS Continued Entered by VVERA1 - IS CONTINUED, CONTRACTOR WORKING ON FINE GRADING PAD ELEVATIONS, AND INSTALLATION OF UTILITIES.
01/21/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /NO CONCERNS AT IS 6801 E BENSON HY
01/21/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN/ NO CHANGE ON SITE AS OF TODAY 6890 E CAMINO BOLEADORAS
01/21/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN/ NO CHANGE ON SITE AS OF TODAY AND NO CONCERNS AT IS TIME. 6601 E BENSON HY
06/25/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED, CREWS CONTINUE TO WORK ON GRADING THE PADS AND THEIR OUTER SLOPES, INSTALLING PIPES AND UTILITIES AT VARIOUS LOCATIONS, FINISH GRADING AND COMPACTING SOME OF THE ROADWAYS AS NEEDED ONCE THE UTILITIES ARE COMPLETED, AND SPREADING WATER AROUND THE SITE TOO ENSURE THAT CONSTRUCTION DUST IS AS MINIMAL AS POSSIBLE.
06/25/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED, CREWS CONTINUE TO WORK ON GRADING THE PADS AND THEIR OUTER SLOPES, INSTALLING PIPES AND UTILITIES AT VARIOUS LOCATIONS, FINISH GRADING AND COMPACTING SOME OF THE ROADWAYS AS NEEDED ONCE THE UTILITIES ARE COMPLETED, AND SPREADING WATER AROUND THE SITE TOO ENSURE THAT CONSTRUCTION DUST IS AS MINIMAL AS POSSIBLE.
06/25/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED, CREWS CONTINUE TO WORK ON GRADING THE PADS AND THEIR OUTER SLOPES, INSTALLING PIPES AND UTILITIES AT VARIOUS LOCATIONS, FINISH GRADING AND COMPACTING SOME OF THE ROADWAYS AS NEEDED ONCE THE UTILITIES ARE COMPLETED, AND SPREADING WATER AROUND THE SITE TOO ENSURE THAT CONSTRUCTION DUST IS AS MINIMAL AS POSSIBLE.
05/14/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - 6890 CONTINUED. GRADING SITE FOR FUTURE PADS, ROADWAY SUBGRADE, AND FUTURE UTILITY INSTALATIONS.
05/14/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - 6601 CONTINUED. GRADING SITE FOR FUTURE PADS, ROADWAY SUBGRADE, AND FUTURE UTILITY INSTALATIONS.
05/14/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED. GRADING SITE FOR FUTURE PADS, ROADWAY SUBGRADE, AND FUTURE UTILITY INSTALATIONS.
04/16/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - CONTINUED, INITIAL GRADING AT THIS TIME
03/04/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED 6809 E CAMINO BOLEADORAS AT THIS TIME. CLEARING OF THE GRADE FOR VEGETATION IS BEING DONE BY THE CONTRACTOR. PILES OF OLD MATERIAL AND VEGETATION ARE BEING CREATED, THESE WILL EITHER BE REMOVED OR MULCHED AT A LATER DATE.
03/04/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 6601 E BENSON HWY AT THIS TIME. CLEARING OF THE GRADE FOR VEGETATION IS BEING DONE BY THE CONTRACTOR. PILES OF OLD MATERIAL AND VEGETATION ARE BEING CREATED, THESE WILL EITHER BE REMOVED OR MULCHED AT A LATER DATE.
01/19/2023 ENGR Grading Final Complete (Recurring) Most of those lots are still under construction
01/19/2023 ENGR Grading Final Complete (Recurring) Most of those lots are still under construction
01/19/2023 ENGR Grading Final Complete (Recurring) Most of those lots are still under construction
01/20/2023 ENGR Grading Final Not Ready Complete all work on this site according to the approved plans prior to calling in for a final inspection
05/01/2023 ENGR Grading Final Complete (Recurring)
05/01/2023 ENGR Grading Final Complete (Recurring)
05/03/2023 ENGR Grading Final Complete (Recurring) Lots are still under construction
05/07/2024 ENGR Grading Final Not Ready COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS PRIOR TO SCHEDULING THIS INSPECTION
05/07/2024 ENGR Grading Final Not Ready COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS PRIOR TO SCHEDULING THIS INSPECTION
09/29/2023 ENGR Grading Final Not Ready Complete all the work on this site as shown on the approved plans prior to calling in this inspection for a final
09/29/2023 ENGR Grading Final Not Ready Complete all the work on this site as shown on the approved plans prior to calling in this inspection for a final
09/29/2023 ENGR Grading Final Not Ready Complete all work on this site prior to calling this Inspection, additional request for this Inspection may result in additional Charges be added for Re-Inspection of a Permit that is not ready. The Inspection that should be scheduled is the Stormwater Follow-up every 2 weeks. Contact David Roberts at (520) 349-7643 to discuss what Inspections need to be called and at what times.
10/28/2022 ENGR Grading Final Partial Pass
10/28/2022 ENGR Grading Final Partial Pass
10/28/2022 ENGR Grading Final Partial Pass