Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP20-0135
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
04/27/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VLEON1 - Partially approved. Wing walls at concrete overflow. |
04/07/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Adam with Bfl. Requesting help scheduling inspection for basin overflow inspection. |
03/24/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Drainage channel bottom. Courtesy inspection for David with Bfl. |
09/29/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Tucson water on site. No other activity at this time. Note reclaimed water facility excessive smell from apparent leak. |
06/15/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. No site work at this time. David with Bfl 392-4255 |
01/29/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - CONTINUE - PLANS RECEIVED FROM JENNIFER WITH BFI. |
10/07/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Water utility work |
08/11/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Final grading. |
03/25/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. No activity on site at this time |
03/18/2022 | ENGR Grading Final | DROBERTS | Correction Required | Entered by VVERA1 - IS CORRECTIONS REQUIRED IN REGARDS TO THE WATER FACILITY ON THIS SITE |
02/24/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - Continued. No activity on site at this time. |
01/11/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - Continued. Masonry work at the station. No site work at this time. |
01/06/2022 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by NGARCIA3 - Not ready. Basin has small amounts of standing water remaining five days after last rain event. Basin shall drain within 48 hours. |
09/29/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Utility work in progress |
08/27/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. No activity on site on this day. |
08/17/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Minor erosion of building pads and rough cut basin. No issues offsite. |
08/05/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Contractor making preparations to start utility work. |
07/09/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Excavating for lift station. |
06/23/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Build up of pad number one. |
06/18/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Preparation for utility work in progress. David with Bfl |
06/03/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Little activity on site at this time |
05/18/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. No activity on site at this time. Temporary fencing installed gate locked |
04/27/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VLEON1 - Partially approved. Wing walls at concrete overflow. |
04/21/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Little activity on site. Contractor completing basin overflow. |
04/13/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Rough grading and utility preparation’s |
04/08/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VLEON1 - PARTIAL APPROVAL BASIN CONCRETE OVERFLOW |
03/31/2021 | ENGR Grading Final | DROBERTS | Continued | Entered by RSALDAT1 - CONTINUED AT THIS TIME. THE CONTRACTOR US WORKING ON GRADING MOST OF THE FUTURE PADS, ANS ALSO IS WORKING ON THE CON-ARCH AREA AT THE NORTH WEST CORNER OF THE SITE. THEY HAVE POURED THE FOOTERS FOR THE STRUCTURE AND ARE CURRENTLY WORKING ON INSTALLING THE WALL AND ROOF REBARS FOR THE STRUCTURE. |
03/25/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Basin overflow connection to existing drainage canal at northwest corner. Rough grading and material import mostly complete. |
03/19/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Continuous importing of materials onto site for One more week. David with BFL at Princeton |
03/18/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - CONTINUE GRADING MATERIAL HAULING IN PROGRESS |
02/23/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. Materials are being tracked onto the site. Grading in progress |
02/05/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Grading site. David with Bfl |
02/06/2024 | ENGR Grading Final | Not Ready | Grading activities have stopped. Stabilization is required. | |
06/27/2024 | ENGR Grading Final | Partial Pass | rough grading and basic stabilization and perimeter fencing have been completed at this time. | |
10/05/2023 | ENGR Grading Final | Partial Pass | ||
10/25/2023 | ENGR Grading Final | Partial Pass | ||
10/25/2023 | ENGR Grading Final | Partial Pass | ||
12/13/2023 | ENGR Grading Final | Partial Pass | Grading activities in progress. No stabilization has been provided. | |
12/29/2023 | ENGR Grading Final | Partial Pass | Provides stabilization as required | |
12/29/2023 | ENGR Grading Final | Partial Pass | recent Grading activities along northern and northwestern portion of site. No stabilization has been provided at this time. |