Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP20-0129
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/22/2021 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - NORTHERN PORTION TO BE COMPLETED IN PHASE 2 |
01/19/2021 | ENGR Engineering Final | MHERNANDEZ | Continued | Entered by VLEON1 - |
12/22/2020 | ENGR Engineering Final | DROBERTS | Not ready for Inspection | Entered by RSALDAT1 - IS NOT READY AT THIS TIME. COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS, PROVIDE US WITH AN APPROVED REVISED DRAWING FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITE. |
12/22/2020 | ENGR Engineering Final | DROBERTS | Approved | Entered by RSALDAT1 - IS APPROVED |
06/24/2020 | ENGR Engineering Final | JV | Prior to Final Inspectn | Entered by JVWINKL1 - This project will require a pre-construction meeting prior to issuance of the development package permit. Project will require EOR certification prior to final inspection 1) This project proposes a disturbance of more than 1 acre or part of a project which will ultimately disturb greater than 1 acre and/or requires a storm water pollution prevention plan |