Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP20-0129

Parcel: 117200270


Addresses:

180 S CHURCH AV


Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP20-0129

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
01/22/2021 ENGR Engineering Final DROBERTS Approved Entered by DROBERT5 - NORTHERN PORTION TO BE COMPLETED IN PHASE 2
01/19/2021 ENGR Engineering Final MHERNANDEZ Continued Entered by VLEON1 -
12/22/2020 ENGR Engineering Final DROBERTS Not ready for Inspection Entered by RSALDAT1 - IS NOT READY AT THIS TIME. COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS, PROVIDE US WITH AN APPROVED REVISED DRAWING FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITE.
12/22/2020 ENGR Engineering Final DROBERTS Approved Entered by RSALDAT1 - IS APPROVED
06/24/2020 ENGR Engineering Final JV Prior to Final Inspectn Entered by JVWINKL1 - This project will require a pre-construction meeting prior to issuance of the development package permit. Project will require EOR certification prior to final inspection 1) This project proposes a disturbance of more than 1 acre or part of a project which will ultimately disturb greater than 1 acre and/or requires a storm water pollution prevention plan