Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP20-0120
Inspection Description - ENGR Grading Final
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by NGARCIA3 - APPROVED 2235 E FORT LOWELL RD |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by NGARCIA3 - APPROVED 2233 E FORT LOWELL RD |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by NGARCIA3 - APPROVED 2229 E FORT LOWELL RD |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by NGARCIA3 - APPROVED 2225 E FORT LOWELL RD |
| 06/16/2022 | ENGR Grading Final | DROBERT5 | Approved | Entered by DROBERT5 - |
| 06/16/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. North basin under construction. Landscaped areas under construction. Material piles in private roadway. Plan in revision status. 2225 E FORT LOWELL RD |
| 06/15/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VVERA1 - Partially approved. Unscheduled courtesy inspection for Jeff the builder.Three Ballard footings. |
| 06/02/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. On-site meeting with Geoff and Dave to discuss remaining work and plan changes. 2225 E Fort Lowell Rd, |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - PARTIAL, COMPLETE THE INSTALLATION OF ALL BASINS PRIOR TO THIS INSPECTION BEING PLACED IN FINALE STATUS 2235 E FORT LOWELL RD |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - PARTIAL, COMPLETE THE INSTALLATION OF ALL BASINS PRIOR TO THIS INSPECTION BEING PLACED IN FINALE STATUS 2233 E FORT LOWELL RD |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL, COMPLETE THE INSTALLATION OF ALL BASINS PRIOR TO THIS INSPECTION BEING PLACED IN FINALE STATUS 2229 E FORT LOWELL RD |
| 06/02/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL, COMPLETE THE INSTALLATION OF ALL BASINS PRIOR TO THIS INSPECTION BEING PLACED IN FINALE STATUS 2225 E FORT LOWELL RD |
| 05/27/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by VVERA1 - IS CONTINUED, HAVE LOOKED AT THE SITE TO VERIFY THAT THE WORK IS PER THE APPROVED PLANS. MINOR CHANGES HAVE BEEN MADE TO THE ROADWAY AND THE GRADES, THESES DO NOT APPEAR TO CAUSE SIGNIFICANT CHANGES BUT WILL HAVE TO BE REVISED ON THE FINAL DRAWINGS. |
| 05/26/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - Continued. Material stock piles arriving on site |
| 05/24/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continue. Grading in preparation for asphalt. Steve 2225 E Fort Lowell Rd |
| 05/17/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued Jeff, sidewalks. 2225 E Fort Lowell Rd, |
| 05/13/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VVERA1 - Partially approved. Forms for concrete sidewalk appear to be within compliance. |
| 05/13/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Forms for concrete sidewalk appear to be within compliance. 2229 E FORT LOWELL RD |
| 05/13/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Forms for concrete sidewalk appear to be within compliance. 2235 E FORT LOWELL RD |
| 05/05/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - IS CONTINUED, LOOKED AT THE FORMS FOR THE CURBS AND SIDEWALKS, OK TO POUR. 2235 E FORT LOWELL RD |
| 05/05/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - IS CONTINUED, LOOKED AT THE FORMS FOR THE CURBS AND SIDEWALKS, OK TO POUR. 2233 E FORT LOWELL RD |
| 05/05/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - IS CONTINUED, LOOKED AT THE FORMS FOR THE CURBS AND SIDEWALKS, OK TO POUR. 2229 E FORT LOWELL RD |
| 05/05/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - CONTINUED, LOOKED AT THE FORMS FOR THE CURBS AND SIDEWALKS, OK TO POUR. 2225 E FORT LOWELL RD |
| 04/26/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Curbs 2225 E Fort Lowell Rd, |
| 04/19/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Install curbs and walkways as shown on plans. Contain all materials within site. 2235 E FORT LOWELL RD |
| 04/19/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Install curbs and walkways as shown on plans. Contain all materials within site. 2233 E FORT LOWELL RD |
| 04/19/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Install curbs and walkways as shown on plans. Contain all materials within site. 2229 E FORT LOWELL RD |
| 04/19/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Jeff at 358-0209. Work outside of the property boundary within the City of Tucson right away, requires is City of Tucson department of transportation right away permit and inspection. Development services inspects within your property boundaries. 2225 E FORT LOWELL RD |
| 04/08/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Utility work within the right of way Requires department of transportation inspection 2225 E Fort Lowell Rd |
| 03/31/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Progress on last building 2225 E Fort Lowell Rd, |
| 03/17/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Excavation work in progress 2025 E Fort Lowell Rd, |
| 11/10/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Geoff on site. Debris piles and other materials on site. All materials are contained within the site |
| 11/02/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Utility work and building construction in progress. Contractor on site. Planning to start installing sidewalks. Requested intermediate inspections as necessary |
| 10/21/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Fourth building construction |
| 10/07/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - 09185. Continued. Unscheduled inspection. Grading and utility work |
| 09/16/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Construction on fourth unit in progress. Material and debris piles on site. |
| 09/02/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. No activity on site on this date. Gate is closed 2225 E FORT LOWELL RD |
| 06/16/2022 | ENGR Grading Final | DROBERT5 | Approved | Entered by DROBERT5 - |
| 06/16/2022 | ENGR Grading Final | DROBERT5 | Approved | Entered by DROBERT5 - |
| 07/16/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continue unscheduled inspection. No obvious issues with that last rain event. Track out protection rock has been installed. Note, building pad elevation was raised to a level higher than existing grade. |
| 07/09/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. unscheduled inspection initiated by Loren Makus. Residential site has been rough graded and two structures have been built. There is no inspection history for the development package. Jeff with JBR custom homes, North Dodge grading contractor and Palm tree homes site developer. Please schedule a 09150 preconstruction meeting for DP20 -0120. It was suggested to Jeff that track out protection be installed as well as Stormwater controls as needed to contain the site. |