Permit: DP20-0119

Parcel: 13304035G


Addresses:

9411 E SPEEDWAY BL


Inspection Status: Not Ready

Inspection History: PDSD Engineering Division Pre-Construction SITE

Permit Number - DP20-0119

Inspection Description - PDSD Engineering Division Pre-Construction SITE

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/26/2022 PDSD Engineering Division Pre-Construction SITE Not Ready
01/12/2021 PDSD Engineering Division Pre-Construction SITE DROBERTS Partial Approval Entered by VLEON1 - PARTIAL AT THIS TIME. I WENT TO THE SITE AT 7:30 am AND WALKED THE SITE PRIOR TO THE PRE-CON MEETING STARING. AT 8:00AM THE MEETING STARTED AND WE DISCUSSED WHAT WOULD BE NEEDED FOR THE SITE TO BEGIN, AND THE EXPECTATIONS THROUGH OUT THE CONSTRUCTION OF THIS SITE. THERE WILL BE SOME CHALLENGES WITH THIS SITE IN THE FUTURE DUE TO EXISTING DRAINAGE PATTERN OFF OF SPEEDWAY BL AND THE ADJACENT PROPERTY OF WALGREENS. THE MEETING WAS CONCLUDED AT AROUND 8:40