Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
Permit Number - DP20-0080
Inspection Description - PDSD Engineering Division Pre-Construction SITE
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/07/2021 | PDSD Engineering Division Pre-Construction SITE | BBENEDON | Approved | Entered by RSALDAT1 - 09150. 09152. Approved. |
12/02/2020 | PDSD Engineering Division Pre-Construction SITE | RLEDONNE | Approved | Entered by PAHUMAD1 - Approved. Met with Danny and two new superintendence for The job. Went over calling in every two weeks for a follow up stormwater. Property line in is what we look at. Providing stormwater controls before starting grubbing have us come back to look at controls in place. |
12/02/2020 | PDSD Engineering Division Pre-Construction SITE | RLEDONNE | Approved | Entered by PAHUMAD1 - Approved. Met with Danny and two new superintendence for The job. Went over calling in every two weeks for a follow up stormwater. Property line in is what we look at. Providing stormwater controls before starting grubbing have us come back to look at controls in place. |
11/17/2020 | PDSD Engineering Division Pre-Construction SITE | RLEDONNE | Continued | Entered by PAHUMAD1 - Continue. Phone message was to set up preconstruction meeting with engineering and preconstruction meeting for site sewer. Past phone number onto Dave Roberts to set up meeting and get with Armando to have combined preconstruction meeting. |