Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 09/07/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by RSALDAT1 - 09150. 09152. Approved. |
| 12/02/2020 |
PDSD Engineering Division Pre-Construction SITE |
RLEDONNE |
Approved |
Entered by PAHUMAD1 - Approved. Met with Danny and two new superintendence for The job. Went over calling in every two weeks for a follow up stormwater. Property line in is what we look at. Providing stormwater controls before starting grubbing have us come back to look at controls in place.
|
| 12/02/2020 |
PDSD Engineering Division Pre-Construction SITE |
RLEDONNE |
Approved |
Entered by PAHUMAD1 - Approved. Met with Danny and two new superintendence for The job. Went over calling in every two weeks for a follow up stormwater. Property line in is what we look at. Providing stormwater controls before starting grubbing have us come back to look at controls in place.
|
| 11/17/2020 |
PDSD Engineering Division Pre-Construction SITE |
RLEDONNE |
Continued |