Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 09/07/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Final grading and preparation for asphalt in progress. Work within the right of way in progress. Temporary fencing and barricades in place.
|
| 06/17/2022 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by NGARCIA3 - IS CONTINUED CREWS WORKING ON UTILITY INSTALLATIONS AND MINOR GRADING THROUGHOUT THE SITE
|
| 01/28/2022 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by NGARCIA3 - CREWS ARE PERFORMING SEWER LINE INSTALLATIONS AT THIS TIME.
|
| 11/14/2023 |
ENGR Grading Final |
|
Passed |
|
| 11/14/2023 |
ENGR Grading Final |
|
Passed |
|