Permit: DP20-0073

Parcel: 13213099A

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP20-0073

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
09/03/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
09/03/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
11/03/2020 ENGR Grading Final BBENEDON Continued Entered by PAHUMAD1 - Continued work on storm drain piping and systems
09/29/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Temporary fence and stormwater protections have been installed. There’s no activity on the side of the street
09/15/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Mike with Chase builders @ 390-5542 plans to start hotel project next week if possible. Permit is in approved status. Please schedule a 09150 Preconstruction meeting inspection when ready.
09/09/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 1420 E TUCSON MARKETPLACE BL
09/03/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
04/09/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - 1590 CONTINUED AT THIS TIME, INSPECTION SCHEDULED FOR TODAY IS FOR LIGHT POLE FOUNDATIONS, THESE ARE TO BE INSPECTED BY THE BUILDING INSPECTOR UNDER THE COMBO PERMIT. THIS INSPECTION HAS BEEN PERFORMED BY DAVID MUNIZ.
04/09/2021 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - 1420 CONTINUED AT THIS TIME, INSPECTION SCHEDULED FOR TODAY IS FOR LIGHT POLE FOUNDATIONS, THESE ARE TO BE INSPECTED BY THE BUILDING INSPECTOR UNDER THE COMBO PERMIT. THIS INSPECTION HAS BEEN PERFORMED BY DAVID MUNIZ.
04/07/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1590 E TUCSON MARKETPLACE BL - FIVE LIGHT POLE FOUNDATION ARE GOOD .CONTRACTOR WILL SEND ME APHOTO OF THE OTHER TWO FOUNDATION.
04/07/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1420 E TUCSON MARKETPLACE BL - FIVE LIGHT POLE FOUNDATION ARE GOOD .CONTRACTOR WILL SEND ME APHOTO OF THE OTHER TWO FOUNDATION.
03/16/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 1590 E TUCSON MARKETPLACE BL - GRO\UTES THE LAST TWO FOOT AND THE BOND BEAM FOR THE TRASH BIN .TOOK SOME PHOTO . THE SMALL WALL WAS GROUTED TOO AND HAVE PHOTO OF IT
03/16/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1420 E TUCSON MARKETPLACE BL - GRO\UTES THE LAST TWO FOOT AND THE BOND BEAM FOR THE TRASH BIN .TOOK SOME PHOTO . THE SMALL WALL WAS GROUTED TOO AND HAVE PHOTO OF IT
03/15/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1590 E TUCSON MARKETPLACE BL. NOT RREADY FOR INSPECTION YET RESCHEDULE FOR TOMORROW AT 11:00 AM.
03/15/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1420 E TUCSON MARKETPLACE BL . NOT RREADY FOR INSPECTION YET RESCHEDULE FOR TOMORROW AT 11:00 AM.
03/12/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - PARTIAL FOR 1590 E TUCSON MARKETPLACE BLVD - OK TO GROUT THE FIRST 4 FEET OF THE WALLS AT THIS TIME
03/12/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - PARTIAL FOR 1420 E TUCSON MARKETPLACE BLVD - PARTIAL, OK TO GROUT THE FIRST 4 FEET OF THE WALLS AT THIS TIME
02/04/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE, POURING FOOTER FOR TRASH BIN
02/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1590 E TUCSON MARKETPLACE BL POURING FOOTER FOR TRASH BIN
02/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1420 E TUCSON MARKETPLACE BL POURING FOOTER FOR TRASH BIN
02/02/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - 1590 E TUCSON MARKET PLACE
02/01/2021 ENGR Grading Final MHERNANDEZ Denied Entered by VLEON1 - DENIED FOR 1590 E TUCSON MARKETPLACE BL BOLLARDS LAYOUT NOT CORRECT RESCHEDULE FOR TOMORROW
02/01/2021 ENGR Grading Final MHERNANDEZ Denied Entered by VLEON1 - DENIED FOR 1420 E TUCSON MARKETPLAC BL BOLLARDS LAYOUT NOT CORRECT RESCHEDULE FOR TOMORROW
12/15/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Trash enclosure detail provided to Mike
11/19/2020 ENGR Grading Final BBENEDON Partial Approval Entered by PAHUMAD1 - Partially approved, Catch basin rebar.
11/19/2020 ENGR Grading Final BBENEDON Partial Approval Entered by PAHUMAD1 - Partially approved, Catch basin rebar.
11/13/2020 ENGR Grading Final BBENEDON Partial Approval Entered by PAHUMAD1 - . Partially approved. Catch basin per detail PAG 309
09/09/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 1420 E TUCSON MARKETPLACE BL
09/09/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 1590 E TUCSON MARKETPLACE BL
09/03/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
08/11/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - 9185 (GRADING - INTERMEDIATE) CN /GRADING THE PARKING LOT.
06/16/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - NA
06/11/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 1590 E TUCSON MARKETPLACE BL, LOOKING AT THE TRASH ENCLOSURE FLOOR. I HAVE ASKED THE CONTRACTOR TO PROVIDE ADDITIONAL CHAIRS UNDER THE REBAR MAT AND SEND ME A PICTURE ONCE IT IS READY TO POUR.
06/11/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 1420 E TUCSON MARKETPLACE BL, LOOKING AT THE TRASH ENCLOSURE FLOOR. I HAVE ASKED THE CONTRACTOR TO PROVIDE ADDITIONAL CHAIRS UNDER THE REBAR MAT AND SEND ME A PICTURE ONCE IT IS READY TO POUR.
01/25/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 1420 E TUSON MARKETPLACE BL REBAR NOT READY RE-INSPECTION TOMORROW. WATTLES NEED TO BE MAINTENANCE
01/25/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CANCELLED NO ONE ON SITE BEACUES OF RAIN LAST NIGHT
01/08/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - FOR 1590 E TUCSON MARKETPLACE BL - CONTINUED AT THIS TIME, NO CONTACT INFORMATION HAS BEEN PROVIDED FOR THIS INSPECTION.
01/08/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED AT THIS TIME, NO CONTACT INFORMATION HAS BEEN PROVIDED FOR THIS INSPECTION.
11/19/2020 ENGR Grading Final BBENEDON Partial Approval Entered by PAHUMAD1 - Partially approved, Catch basin rebar.
11/13/2020 ENGR Grading Final WGALLAGHER Partial Approval Entered by PAHUMAD1 - Partially approved.
11/06/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Shading and backfilling 24 inch storm drain
11/05/2020 ENGR Grading Final BBENEDON Partial Approval Entered by PAHUMAD1 - Partially approved. 24 inch storm drain piping. Mike with Chase builders
11/04/2020 ENGR Grading Final BBENEDON Continued Entered by PAHUMAD1 - Continued. Excavation continuing for 24 inch storm drain
11/03/2020 ENGR Grading Final BBENEDON Continued Entered by PAHUMAD1 - Continued. Shading and bedding with completion of 48 inch storm drain piping.
10/30/2020 ENGR Grading Final BBENEDON Partial Approval Entered by PAHUMAD1 - Partially approved. 48 inch storm drain from connection to existing onto site. Mike with Chase builders.
10/30/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. 48 inch storm drain from connection to existing onto site. Mike with Chase builders.
10/29/2020 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - MET THE CONTRACTOR AND WITNESSED THE FOLLOWING, 48” PIPE INSTALLED AND BACK FILLED FROM 0 00 TO STATION 0 75, INSTALLING AND BACKFILLING PIPE FROM STATION 0 75 TO STATION 1 25. COLLAR TO BE POURED AT STATION 0 00 AT A LATER DATE, WILL NEED TO VERIFY COLLAR SPECS PRIOR TO CONCRETE PLACEMENT.
10/28/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continue. Excavating for stormwater pipe. Mike with Chase builders will document the installation with pictures and call for daily inspections. OK to cover with daily progress. Inspector needs to see Our connections, piping and bedding and catch basins and manholes.
10/27/2020 ENGR Grading Final BBRENEDON Continued Entered by PAHUMAD1 - Continued. Rough grading has been completed and footings have been poured. Material stock piles on site
10/20/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Over excavation and backfill completed contractor starting building footings.
10/08/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Excavation and material hauling from site in progress.
10/06/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Rough grading has started
10/02/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Existing material removal and rough grading to start