Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP20-0050
Inspection Description - ENGR Grading Final
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2021 | ENGR Grading Final | MHERNANDEZ | Approved | Entered by VLEON1 - |
| 02/10/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE FOR 1054 E TUCSON MARKETPLACE BL- REBAR AND POURING THE FRONT OF THE TRASH BINS |
| 11/06/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Trash enclosure footings |
| 04/06/2021 | ENGR Grading Final | DROBERT5 | Approved | Entered by DROBERT5 - |
| 04/06/2021 | ENGR Grading Final | DROBERT5 | Approved | Entered by DROBERT5 - |
| 04/06/2021 | ENGR Grading Final | DROBERT5 | Approved | Entered by DROBERT5 - |
| 02/10/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE FOR 1054 E TUCSON MARKETPLACE BL - DRIVEWAYS |
| 10/28/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by PAHUMAD1 - Continued. Storm drains and domestic sewer piping has been backfilled. No grading activity at this time. |
| 10/13/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continue. Provide a watertight connection as prescribed in standard detail requirements for building rainwater piping at site stormwater Drain piping 5 feet outside of building foundation. |
| 10/09/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Completion of stormwater piping and manholes. |
| 10/08/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Backfilling piping in Roadway |
| 10/06/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Completing last section of stormwater piping in private roadway. |
| 10/02/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Manholes. |
| 10/01/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Catch basins. |
| 09/30/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Stormwater piping connections to manhole and catch basins |
| 09/29/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Catch basins and manhole bases installed |
| 09/28/2020 | ENGR Grading Final | DROBERTS | Continued | Entered by JSCHNEI2 - CONTINUED AT THIS TIME, SITE LOCKED AND ALL PERSONNEL HAVE LEFT FOR THE DAY AT 3:45PM. CREWS ARE WORKING ON SITE WORK AND PREPARING FOR THE SUB-GRADE FOR THE FLOOR SLAB POUR IN THE FUTURE. THEY HAVE CORRUGATED PLASTIC LAYING ON SITE BUT NOTHING WAS CHECKED ON THIS DATE. |
| 09/25/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Contractors installing pre-manufactured catch basins. |
| 09/24/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Backfill of storm drains. |
| 09/23/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Continuation below grade stormwater piping and shading. |
| 09/22/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. Storm water piping |
| 09/21/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Storm drain from manhole onto site. |
| 09/17/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - continued. Barricades have been installed preparation of manhole connection. Private drive. |
| 09/14/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Courtesy inspection prior to storm drain piping and connections. Plans indicate storm water piping connection point is within a private street indicating no right of way inspections are necessary. Richard will schedule inspections and document all connections and piping for inspection. |
| 09/04/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - . Continued. Contractor has started over excavation and site sewer. Magnum contracting and Barker Morisey |