| 10/05/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN POURED THE ADOT COLLAR |
| 09/27/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /FORMING A ADOT COLLAR GOOD
1002 E 36TH ST |
| 09/27/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /FORMING A ADOT COLLAR GOOD
2805 S PARK AV |
| 09/26/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /CONTRACTOR CALL NEED TO RESCHEDULE |
| 09/26/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /CONTRACTOR CALL NEED TO RESCHEDULE |
| 09/14/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN GOOD AT IS TIME |
| 08/31/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN FORMING ONE CATCH BASIN AND ONE COLLAR. |
| 08/23/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN
2805 S PARK AV |
| 08/23/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN
1002 E 36TH ST |
| 08/03/2022 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Partial Approval |
Entered by VVERA1 - Partially approved. Track out protection rock installed at North and West site entrances. Waddle installed along west perimeter fencing.
Minor track out noted on 36th St. |
| 07/28/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /NO CHANGES GOOD AS OF TODAY
2805 S PARK AV |
| 07/28/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /NO CHANGES GOOD AS OF TODAY
1002 E 36TH ST |
| 07/25/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN NO CHANGES |
| 07/25/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN NO CHANGES |
| 07/21/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /NO REBAR FAILED. NON -COMPLIANCE
2805 S PARK AV |
| 07/21/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /NO REBAR FAILED. NON -COMPLIANCE
1002 E 36TH ST
|
| 07/05/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN |
| 06/30/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN NO CHANGES AS OF TODAY GOOD
2805 S PARK AV |
| 06/30/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN NO CHANGES AS OF TODAY GOOD
1002 E 36TH ST
|
| 06/20/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN
2805 S PARK AV |
| 06/20/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN
1002 E 36TH ST |
| 06/13/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN/ INSTALLING 36’ R.C.P. |
| 06/13/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN./INSTALLING 36” R.C.P.
|
| 06/08/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN INSTALLING 36” R C P AND DP 120 ‘
2805 S PARK AV |
| 06/08/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN INSTALLING 36” R C P AND DP 120 ‘
1002 E 36TH ST |
| 06/02/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN GOOD AS OF TODAY.
2805 S PARK AV |
| 06/02/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN GOOD AS OF TODAY.
1002 E 36TH ST |
| 05/13/2022 |
SITE - Stormwater Setup and Controls |
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - PARTIAL
2805 S PARK AV |
| 05/13/2022 |
SITE - Stormwater Setup and Controls |
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - PARTIAL
1002 E 36TH ST |
| 05/04/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN |
| 01/19/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN FORMING FOR 42” STORMWATER FROM EXISTING TO NEW .
2805 S PARK AV |
| 01/19/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN FORMING FOR 42” STORMWATER FROM EXISTING TO NEW .
1002 E 36TH ST |
| 12/30/2021 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN / HAVE NOT STARTED INSTALLING STORMWATER YET. CONTRACTOR NOT ON SITE.
2805 S PARK AV |
| 12/30/2021 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN / HAVE NOT STARTED INSTALLING STORMWATER YET. CONTRACTOR NOT ON SITE.
1002 E 36TH ST |