Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/21/2022 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 08/01/2022 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/17/2022 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - I MET WITH PETER SALONGA ON SITE TO DISCUSS THE ISSUES THAT I HAVE WITH THE SITE. THE 3 ITEMS THAT WE HAVE DISCUSSED IS:
1) THE COMPLETION OF ALL OPEN AREAS THROUGHOUT THE SITE THAT HAVE BEEN DISTURBERED BUT HAVE NOT BEEN FINISHED. COMPLETE ALL OF THE FINAL GRADING IN AND AROUND THE AREAS AND PLACE THE GROUND COVERING THAT HAS BEEN SPECIFIED ON THE APPROVED PLANS. MOST OF THE AREAS CAN EITHER BE HYDRO SEEDED OR THEY CAN PLACED DECOMPOSED GRANITE OVER THE DISTURBED AREAS.
2) GRADE AND INSTALL ROCK RIP RAP ON FILTER FABRIC IN ALL AREAS NOTEED ON THE APPROVED PLANS. ALSO ON THE NORTHSIDE OF THE PROPERTY ADJACENT TO AN EXISTING DRAINAGE SWALE, 4 - 8 INCH ROCK RIP RAP IS TO BE PLACED INTO A BED OF CONCRETE GROUT DUE TO THE STEEPNESS OF THE SLOPES, NONE OF THIS WORK HAS BEEN DONE AT THIS TIME. CURRENTLY THEY CONTRACTOR HAS PLACED SMALL ROCK ALONG THE FACE OF THE SLOPE WITHOUT EITHER FILTER FABRIC OR GROUT AND THEN LEVELED THE AREA SOUTH OF THE DRAINAGE SWALE, PLACING ALL OF THE LOOSE MATERIAL ON THE UPPER EDGE OF THE SOUTHERN SLOPE OF THE EXISTING CHANNEL.
3) REPAIR THE DAMAGED SIDEWALK AND DRIVEWAY AT THE STREET AND ANY PAVEMENT THAT MAY NEED TO BE REPAIRED IN THE PRIVATE STREET ADJACENT TO THIS PROPERTY.
ONCE ALL OF THIS WORK IS COMPLETE PLEASE CONTACT ME AT (520) 349-7643 SO THAT I CAN SCHEDULE ANOTHER INSPECTION FOR THIS SITE AS A FINAL. |
| 04/10/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - |