Permit: DP20-0032

Parcel: 116300390

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP20-0032

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
02/26/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
02/26/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
02/26/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
02/18/2020 ENGR Grading Final DROBERTS Denied Entered by DROBERT5 - I CAME TO THIS SITE TODAY TO TAKE SOME CROSS SLOPE READINGS OF THE SIDEWALKS AND DRIVEWAY FOR THIS SITE SO THAT THIS INFORMATION CAN BE PASSED ONTO THE BUILDING OFFICIAL AS WELL AS TO THE REVIEW STAFF TO TRY AND DETERMINE WHAT CAN BE DONE WITH THIS SITE TO MAKE IT MEET THE COMPLIANCE FOR ADA.
02/14/2020 ENGR Grading Final DROBERTS Denied Entered by DROBERT5 - I WALKED THE SITE WITH THE CONTRACTOR FOR THE FINAL APPROVAL, BUT AM UNABLE TO PASS IT AT THIS TIME SINCE IT WAS CONSTRUCTED WITHOUT A DEVELOPMENT PACKAGE AS PREVIOUSLY NOTED. CURRENTLY THE BIG ISSUE OUTSIDE OF THE LACK WITHOUT A PERMIT IS THAT THE SIDEWALK AND DRIVEWAY ARE NON COMPLIANT AND NEED TO BE ADDRESSED PRIOR TO THE FINAL APPROVAL OF THIS SITE. I HAVE ASKED THE CONTRACTOR TO CONTACT HIS ENGINEER FOR THIS SITE AND ARRANGE TO GO DOWNTOWN AND DISCUSS THIS SITE WITH STEVE SHIELDS / ZONING AND JOHN VAN WINKLE WITH ENGINEERING TO TRY AND DETERMINE WHAT IS GOING TO BE REQUIRED TO CLOSE OUT THIS PROJECT. THE CROSS SLOPE OF THE SIDEWALK VARIES FROM 1.5% TO 15% AT VARIOUS LOCATIONS, THESE EXCEED THE MAXIUM ALLOWABLE OF 2%. THIS INSPECTION WAS TO BE CHARGED A SAME DAY INSPECTION FEE, BUT I HAVE NOT CHARGED THIS FEE DUE TO THE FACT THAT THE SITE IS NOT READY TO BE APPROVED. WE LOOKED AT VARIOUS SITUATIONS IN WHICH HE MIGHT BE ABLE TO ACHIEVE THE ADA COMPLIANCE, HE WILL DISCUSS THIS SITE WITH THE ARCHITECT FOR THE SITE AND THEN WILL MEET WITH THE REVIEW STAFF DOWNTOWN TO FIND THE BEST SOLUTION.
02/26/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
02/25/2020 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - MET WITH THE CONTRACTOR AND LOOKED OVER THE WORK THAT THEY ARE CURRENTLY DOING. 1) THEY HAVE REMOVED AND REPLACED THE PAVERS IN THE DRIVEWAY IN THE FIRST R FEET BEHIND THE WEDGE CURB. SOME OF THIS NEEDS TO BE REDONE DUE TO THE FACT THAT IT EXCEEDS THE 2% AS REQUIRED FOR ADA ACCESSIBLE ACCESS. I HAVE ADVISED THE CONTRACTOR OF THE REQUIRED MODIFICATIONS NEED PRIOR TO THE FINAL ACCEPTANCE. 2) CREWS ARE ALSO WORKING ONREWORKING THE DRAINAGE SWALE ON THE NORTH SIDE OF THE PROPERTY. THEY HAVE COMPLETED THE EASTERN HALF AND ARE WORKING ON CUTTING THE SWALE ON THE WESTERN HALF. 3) THE LAST ITEM THAT IS BEING COMPLETED IS PLACING GROUT IN ROCK WALL ALONG THE SOUTHSIDE OF THE PROPERTY. THIS PORTION OF THE WORK WILL BE COMPLETED POSSIBLY BY THE END OF THE DAY TODAY, IT WILL BE SCHEDULED FOR INSPECTION TOMORROW.