Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 02/19/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by VLEON1 - CONTINUED FOR 2574 N DRAGOOD ST, CONTRACTOR CUTTING THE GRADE FOR THE ABC, CREWS PLANNING ON PAVING TOMORROW.
|
| 02/19/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by VLEON1 - CONTINUED, CONTRACTOR CUTTING THE GRADE FOR THE ABC, CREWS PLANNING ON PAVING TOMORROW. |
| 10/05/2020 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - LOOKED AT THENEW CATCHBASIN FOR THIS SITE THEY WILL ADVISE ME WHEN THEY POUR IT. |
| 10/02/2020 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - LOOKED AT THE PLACEMENT OF 24 INCH HDPE ONTHE WEST SIDE OF THIS PROJECT. I HAVE ADVISED ZAC/CANYON THAT THIS INSPECTION IS GOOD FOR THE SOUTHERN PORTION OF THIS PIPE RUN BUT WE WILL NEE TO INSPECT THE NEW CATCHBASN AS WELL AS THE TIE-IN TO THE EXISTING WASH AT A LATER DATE. THE PIPE INSPECTION WILL B E SCHEDULED FOR NEXT WEEK WHEN THEY CALL FOR THE INSPECTION. |