Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 07/20/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approved. Lyle with sundt at480-229-0120
Has installed controls around existing basin and at entry to the site. Will call for regular inspections of SWPPP and for all below grade stormwater piping and connections. Has hired a contractor to comply with recent change
To SWPPP permitting |
| 04/13/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Parking garage at TCC. Lyle with. 480-2 29-0120. Contractor installing temporary fence and preparing to remove asphalt and grub site. Contractor has an noi post SWPPP. Install controls as required. Please call for stormwater inspections on a regular basis.
Provide 6 inches of depressed landscaped areas as shown. Provide a right away permit and inspections for all work outside of Property.
Granier engineering Jason Morse 326-7082.
Desert survivors is responsible for Stormwater’s. Hallmark will be doing native plant preservation. |