Inspection Status: Passed
Inspection History: SITE - Stormwater Setup and Controls
| Date |
Description |
Inspector |
Results |
Comments |
| 11/17/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Approved |
Entered by PAHUMAD1 - |
| 09/17/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Partial Approval |
Entered by JSCHNEI2 - partially approved. New signage has been installed as required. |
| 09/17/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Partial Approval |
Entered by JSCHNEI2 - partially approved. New signage has been installed as required.
|
| 07/20/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Controls are in place. Additionally contractor has hired Derric Pooler as a stormwater consultant and will comply with the new SWPPP requirements. Lyle with sundt. |
| 04/24/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Temporary fencing, waddle, check out protection and signage has been installed. Lyle at 480-290-0120. |
| 04/24/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - . Partially approved. Temporary fencing, waddle, check out protection and signage has been installed. Lyle at 480-290-0120. |