Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP19-0300

Parcel: 10321025H

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP19-0300

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
04/28/2022 ENGR Grading Final BBENEDON Approved Entered by NGARCIA3 - Approved
04/28/2022 ENGR Grading Final BBENEDON Approved Entered by NGARCIA3 - Approved
04/04/2022 ENGR Grading Final DROBERTS Continued Entered by VVERA1 - IS CONTINUED AT THIS TIME, CREWS ARE WORKING ON THE LANDSCAPING ITEMS AND INSTALLING ANTS AS NEEDED AND PREPARING TO POUR THE CONCRETE STORM DRAINS.
03/14/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL AT THIS TIME, WALKED THE SITE WITH THE CONTRACTOR TO SEE WHAT CONCERNS BRIAN BENEDON HAS RAISED. THE ROOF DRAINAGE FOR THE SITE IS BEING DIRECTED MOSTLY TO THE STREET AND IS NOT MEETING THE STORMWATER PLANS THAT HAVE BEEN APPROVED. I HAVE ADVISED THE SUPERVISOR. HUCK WITH APN THAT WE WILL NEED TO SEE AN APPROVED REVISED DRAWING FOR ALL THE CHANGES BEFORE WE WILL LET THEM IMPLEMENT THEM IN THE FIELD. ALSO THERE ARE SOME OTHER CHANGES THAT MAY NEED TO BE MADE TO SIDEWALKS AN CURBS ON THIS SITE BEFORE THE FINAL CAN BE ACCEPTED. WE WILL WALK THIS SITE NEXT WEEK AND DISCUSS ALL THE CHANGES AT THAT TIME.
03/08/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Contractor grading for landscaped areas
02/03/2022 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Perimeter wall, front.
01/25/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Final grading in progress
01/19/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Courtesy unscheduled inspection. Ron’s concrete installing sidewalks.
01/13/2022 ENGR Grading Final BBENEDON Partial Approval Entered by VVERA1 - Partially approved. Curb installation in progress
12/01/2021 ENGR Grading Final BBENEDON Partial Approval Entered by NGARCIA3 - Par. Catch basin inlet
11/24/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Grading
11/02/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Grading and Light pole footings installed
10/26/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Rough grading
09/07/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Contractor erecting building number three
06/28/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CREWS ARE WORKING ON THE BUILDING FOOTINGS, UTILITIES, AND FORMING AT THIS TIME.
04/29/2022 ENGR Grading Final BBENEDON Approved Entered by VVERA1 - 9190.Approved. Please change permit status to final.
03/21/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN/FORMING THE APRON FOR THE TRASH BIN FLOOR.
11/05/2021 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 - . Approved
10/19/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Trash enclosure slabs have been poured within enclosure. Apron has not been installed
10/11/2021 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN / SETTING THE REBAR FOR THE FLOOR FOR TRASH BIN THREE OF THEM.
09/22/2021 ENGR Grading Final BBENEDON Partial Approval Entered by VVERA1 - 09181, Partially approved. Trash enclosure pre-grout, three buildings. Photograph documentation from superintendent Chuck via text
09/21/2021 ENGR Grading Final BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. Pre-grout. Chuck
09/15/2021 ENGR Grading Final BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. 3 Trash enclosure footings. Chuck
09/14/2021 ENGR Grading Final BBENEDON Not ready for Inspection Entered by VVERA1 - 09181. Not ready. Chuck at 400 2709. Provide number four rebar at 32 inches on center vertical. Schedule inspections from development package permit
04/29/2022 ENGR Grading Final BBENEDON Approved Entered by VVERA1 - Approved. Please change permit status to final.
04/23/2020 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - THIS PLAN HAS BEEN APPROVED AND IS CURRENTLY ON THE APPROVED SHELF WAITING TO BE ISSUED