Permit: DP19-0300

Parcel: Unknown

Inspection Status: Passed

Inspection History: ENGR Engineering Final

Date Description Inspector Results Comments
04/29/2022 ENGR Engineering Final BBENEDON Approved Entered by VVERA1 - Approved. Please change permit status to final.
04/27/2022 ENGR Engineering Final BBENEDON Partial Approval Entered by VVERA1 - Partially approved
04/26/2022 ENGR Engineering Final BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. Chuck with WAPN builders
04/29/2022 ENGR Engineering Final BBENEDON Approved Entered by VVERA1 - Approved. Please change permit status to final.
04/28/2022 ENGR Engineering Final BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. Provide notice of termination for SWPPP
03/08/2022 ENGR Engineering Final BBENEDON Not ready for Inspection Entered by VVERA1 - Not ready. Contractor informed that sidewalk scuppers are necessary or needed and that he should contact the project engineer for further instruction