Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 11/20/2020 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by PAHUMAD1 - |
| 11/06/2020 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by RSALDAT1 - IS NOT READY AT THIS TIME, ONLY PORTIONS OF THE PAVEMENT HAS BEEN COMPLETED AT THIS TIME. I TALKED TO THE SITE SUPERVISOR AND HAVE BEEN ADVISED THAT THE REMAINING PAVEMENT WILL BE PLACED ON 11/9/2020. THEY WILL BE RESCHEDULING THIS INSPECTION FOR A TCO ON 11/10/2020, LOOKING FOR A TCO ON 11/11/2020.
|
| 12/01/2020 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by PAHUMAD1 - |
| 11/20/2020 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by PAHUMAD1 - PARTIAL AT THIS TIME, FINAL IS PENDING PARKING STRUCTURE CANOPIES |
| 11/10/2020 |
ENGR Engineering Final
|
RLEDONNE |
Partial Approval |
Entered by PAHUMAD1 - Partial approval. OK for TCO . Complete all work on approved plans for final approvals. |