Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 04/27/2023 | ENGR Engineering Final | Not Ready | Trash enclosure installed without inspection. Below ground and parking lot stormwater piping installed without inspection. Provide Documentation of proof that work was installed in compliance with approved plans. complete remaining work as shown on approved plans including basin and water harvesting areas. Riprap, bollards, bicycle, parking, etc. Complete landscaping as shown and approved plans. Also Accessible route as shown between buildings. J with Barker |
|
| 04/27/2023 | ENGR Engineering Final | Not Ready | Trash enclosure installed without inspection. Below ground and parking lot stormwater piping installed without inspection. Provide Documentation of proof that work was installed in compliance with approved plans. complete remaining work as shown on approved plans including basin and water harvesting areas. Riprap, bollards, bicycle, parking, etc. Complete landscaping as shown and approved plans. Also Accessible route as shown between buildings. J with Barker |
|
| 07/25/2023 | ENGR Engineering Final | Passed | see grading comments. |