Inspection Status: Passed
Inspection History: SITE - Stormwater Setup and Controls
| Date |
Description |
Inspector |
Results |
Comments |
| 01/22/2021 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Approved |
Entered by VLEON1 - APPROVED |
| 09/11/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. Trackout protection and concrete washout in place some waddle installed At Northwest perimeter. Install additional model as needed to protect material stock piles
|
| 08/20/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Some controls have been installed at northwest corner however large stock pile of material is unprotected in that corner. Track out protection is in place. |