Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP19-0250
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/20/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - . Approved. |
01/20/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - . Approved |
12/29/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Building construction in progress. Sidewalk construction within the ROW |
10/27/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by PAHUMAD1 - Continued. New superintendent on site is Andy Wilson with Canyon at 312-1663 |
10/12/2020 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by VFLORES1 - OK TO POUR THE CONCRETE FOOTER FOR THE TRASH ENCLOSURE. |
01/21/2021 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - Approved |
10/22/2020 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by RSALDAT1 - IS PARTIAL AT THIS TIME, OK TO PLACE CONCRETE FOR THE FLOOR SLAB.ONCE REBAR MAT HAS BEEN SUPPORTED WITH ADDITIONAL CHAIRS, PENDING PHOTOS. THE CONTRACTOR HAS CONSTRUCTED THE WALLS FULLY SO THE GROUT FOR THE WALLS CAN NOT BE PLACED TILL THE KNOCK AT HOLES FOR GROUT HAS BEEN PROVIDED TO VERIFY GROUT PLACEMENT. I HAVE ASKED THEM TO PHOTOGRAPH THE HOLES AND THE PLACEMENT OF THE REBAR FOR THE REQUIRED BOND BEAM ATTHE TOP OF THE WALLS. |
09/24/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by JSCHNEI2 - Not ready. Contractor has not yet started trash enclosure. |
01/29/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
01/26/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued. No corrections have been made yet at south basin requiring repair. |
01/21/2021 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VLEON1 - PARTIAL, WATER HAVERSTING BASING, PROVEIDE RIP RAP AT INLET, PROVIDE DEPRESSED LANDSCAPED AREAS AS REQUIRED PER PLANS |
10/27/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Accessible walkways around building. Andy Wilson with Canyon builders. |
10/23/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by PAHUMAD1 - CONTINUED. CONSTRUCTING PERIMETER WALL. |
10/22/2020 | ENGR Grading Final | DROBERTS | Continued | Entered by RSALDAT1 - VERTICAL CONSTRUCTION IS HAPPENING ON THIS SITE MAINLY, ALSO LOOKED AT THE TRASH ENCLOSURE. |
09/23/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Building construction in progress |
08/20/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Utility work in progress and in the right of way. Road closure in place. |