Permit: DP19-0214

Parcel: 132131280


Addresses:

3434 S KINO PW


Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Permit Number - DP19-0214

Inspection Description - ENGR Grading Final

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
08/20/2021 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - PARTIAL AT THIS TIME, OK TO POUR THE CENTER AND WESTERN CATCH BASIN ON THE SOUTH SIDE OF THE PROJECT.
08/16/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - 9181 (GRADING - REBAR) CN /FORMING THE CATCH BASIN NORTH EAST.
08/09/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN/ FORMING ONE CATCH BASIN NORTH OF THE MAIN ROAD.
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN /POUTING COLLAR FOR RCP AND ONE CATCH BASIN AND CATCH BASIN FLOOR
08/02/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN./ FORMING FOR TREE CATCH BASIN THE NORTH SIDE OF THE MAIN ROAD.
07/30/2021 ENGR Grading Final DROBERTS Denied Entered by VLEON1 - DENIED. MIKE BAUERS POSTPONED THIS INSPECTION THIS MORNING. CHECKED AFTER LUNCH HE HAS CANCELLED THIS INSPECTION AND WILL RESCHEDULE IT FOR A LATER DATE.
07/28/2021 ENGR Grading Final MHERNANDEZ Cancelled Entered by RSALDAT1 - CONTRACTOR CANCELED TODAY INSPECTION.
07/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN /. CONTRACTOR RESCHEDULE FOR TOMORROW .
12/17/2021 ENGR Grading Final BBENEDON Not ready for Inspection Entered by NGARCIA3 - Not ready. There is no contact information or message provided for this inspection. Please reschedule inspection and provide necessary information for Inspector to complete inspection.
10/15/2021 ENGR Grading Final BBENEDON Not ready for Inspection Entered by NGARCIA3 - Not ready. No contact information provided for inspection. No history of preconstruction meeting. Please schedule a preconstruction meeting and please provide contact information and scheduling inspections.
10/07/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN/ GRADING ANEW ENTRANCE OFF OF KINO .AND PLACING ABC ON THE NORTH END OF THE PROJECT.
09/08/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN /PLACING A.B.C.
07/22/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN/ FORMING TWO CATCH BASIN.
07/19/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CUTTING THE ROAD.
10/11/2023 ENGR Grading Final Not Ready Called Rick engineering # (520) 795-1000 spoke to Vanessa she said she would get me in touch with Janak he called me back (586) 601-4102 this permit was pulled by Borderland construction. it was a general address for the Martin Luther King boulevard extension plat A sections 1 2 and 3, I will review with Dave Roberts.
10/11/2023 ENGR Grading Final Not Ready Called Rick engineering # (520) 795-1000 spoke to Vanessa she said she would get me in touch with Janak he called me back (586) 601-4102 this permit was pulled by Borderland construction. it was a general address for the Martin Luther King boulevard extension plat A sections 1 2 and 3, I will review with Dave Roberts.
10/11/2023 ENGR Grading Final Not Ready Called Rick engineering # (520) 795-1000 spoke to Vanessa she said she would get me in touch with Janak he called me back (586) 601-4102 this permit was pulled by Borderland construction. it was a general address for the Martin Luther King boulevard extension plat A sections 1 2 and 3, I will review with Dave Roberts.
10/11/2023 ENGR Grading Final Not Ready Called Rick engineering # (520) 795-1000 spoke to Vanessa she said she would get me in touch with Janak he called me back (586) 601-4102 this permit was pulled by Borderland construction. it was a general address for the Martin Luther King boulevard extension plat A sections 1 2 and 3, I will review with Dave Roberts.
10/18/2023 ENGR Grading Final Partial Pass
10/18/2023 ENGR Grading Final Partial Pass
10/18/2023 ENGR Grading Final Partial Pass
10/18/2023 ENGR Grading Final Partial Pass Monument on East side of Martin Luther King Jr. is completed and in place and landscape is completed, the Monument on the West side of Martin Luther King Jr. has footer and monument base completed and landscape around concrete base is not complete.

The sidewalks and landscape for this section are about 90 % completed.

Need to verify detail (27) on page 2 and 3 and handicap ramp and railing on West side of MLK Jr.