Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP19-0206

Parcel: 136129420

Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP19-0206

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
06/29/2020 ENGR Engineering Final RLEDONNE Approved Entered by RSALDAT1 - Approved.
08/26/2020 ENGR Engineering Final RLEDONNE Approved Entered by JSCHNEI2 - Approved.
08/17/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by JSCHNEI2 - Not ready. Working on artificial turf on south side of building.
08/10/2020 ENGR Engineering Final RLEDONNE Partial Approval Entered by RSALDAT1 - Partial approval. Working on imitation sod on south side of building.
07/29/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by JSCHNEI2 - Not ready. Working on DG on south side of building.
07/22/2020 ENGR Engineering Final DROBERTS Partial Approval Entered by DROBERT5 - OK FOR A TCO, FENCE ALL AREAS UNDER CONSTRUCTION AT THIS TIME IF STUDENTS ARE ALLOWED ON THIS SITE, OR COMPLETE ALL OF THE REMAINING LANDSCAPE ON THE SOUTH AND WEST SIDES OF THIS SITE.
07/16/2020 ENGR Engineering Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Stabilization on south side of building still has not been done. North side entrance overhead work appears to be complete.
07/13/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by JSCHNEI2 - Not ready. Complete cleanup on outside of building. Provide stabilization to all disturbed areas during construction. Complete overhead work above door on north side of building.Complete striping at drop off area on north side of building.
07/10/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by RSALDAT1 - Not ready. Complete all pedestrian pathways per approved plans.