Permit: DP19-0191

Parcel: 11451218A

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP19-0191

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
03/09/2020 ENGR Grading Final RLEDONNE Approved Entered by DMERANZ1 -
03/04/2020 ENGR Grading Final RLEDONNE Continued Entered by SFLORES2 - Continue. OK for first left on trashing closure.
02/14/2020 ENGR Grading Final DROBERTS Continued Entered by SFLORES2 - IS CONTINUED AT THIS TIME, OK TO POUR FOOTER FOR THE TRASH ENCLOSURE
02/13/2020 ENGR Grading Final RLEDONNE Not ready for Inspection Entered by DMERANZ1 - Concrete contractor did not show up.
06/30/2020 ENGR Grading Final RLEDONNE Approved Entered by RSALDAT1 - Approved.
07/08/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/08/2020 ENGR Grading Final DROBERTS Approved Entered by RSALDAT1 - IS APPROVED
07/06/2020 ENGR Grading Final DROBERTS Not ready for Inspection Entered by RSALDAT1 -
07/01/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Walk site with Dave Roberts Ryan and Craig. Went over work to be completed for finals.
06/30/2020 ENGR Grading Final RLEDONNE Not ready for Inspection Entered by RSALDAT1 - Not ready.ADA parking and drop off zone over 2%. Ramp leading to street over 2% need to add handrails to ramp. Complete bicycle parking. Complete all work on approved plan.
06/16/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Walk site with GC went over work to finish for finals checked water harvesting areas.
05/27/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Walked site with concrete contractor and general contractor Ryan. Went over ramps on site and sidewalks. Any change to approve plans provide COTApproved revisions.
05/08/2020 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 - IS CONTINUED AT THIS TIME. THE CREWS ARE WORKING ON MAKING GRADE THROUGHOUT THIS SITE AND FORMING FOR SIDEWALKS. THEY ARE MAKING SOME MINOR CHANGES TO THE SIDEWALK AT THE SOUTH EAST CORNER OF THE SITE, THEIR RECOMMENDATIONS APPEAR TO BE ACCEPTABLE AND WILL BE SUBMITTED FOR APPROVAL DURING THEIR REVISIONS FOR THE SITE. I HAVE ASKED THE SUPERINTENDENT TO ADVISE THE ENGINEER OF RECORD TO SEND ME A PDF OF THE CHANGE SO THAT I CAN FORWARD IT TO THE ZONING AND ENGINEERING REVIEWERS.
08/24/2021 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 - Continued. Expired permit, brake max. All finals were approved.
06/16/2020 ENGR Grading Final RLEDONNE Approved Entered by RSALDAT1 -
05/08/2020 ENGR Grading Final DROBERTS Continued Entered by RSALDAT1 -