Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP19-0183

Parcel: 105102470


Addresses:

4405 N 1ST AV


Inspection Status: Passed

Inspection History: PDSD Engineering Division Pre-Construction SITE

Permit Number - DP19-0183

Inspection Description - PDSD Engineering Division Pre-Construction SITE

Inspection Status - Passed

Date Description Inspector Results Comments
07/27/2020 PDSD Engineering Division Pre-Construction SITE DROBERTS Approved Entered by RSALDAT1 - IS APPROVED
07/14/2020 PDSD Engineering Division Pre-Construction SITE BBENEDON Partial Approval Entered by JSCHNEI2 - Partially approved. New superintendent on site. Bob With Mw Morrissey. at 444-4351. Make sure all stormwater protections are in place with predicted monsoon storms in the forecast. Please call for stormwater follow up inspections and intermediate. Inspections from development package permit
07/13/2020 PDSD Engineering Division Pre-Construction SITE BBENEDON Denied Entered by JSCHNEI2 - Denied. Terry With Mw Morrissey. at 343-1700 was requested to schedule inspections from the development package permit.And June 23.