Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 01/05/2021 |
ENGR Grading Final |
BBENEDON |
Not Applicable |
Entered by RSALDAT1 - 09181. Not applicable |
| 05/27/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued FOR 2427 N FORGEUS AV .No new activity at this time. Partial temporary fencing in place.
|
| 05/11/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued FOR 2433 N FORGEUS AV. No activity at this time. Temporary fencing on one side of lot in place |
| 04/15/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE FOR 2433 N FORGEUS AV |
| 02/12/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE FOR 2433 N FORGEUS AV, MIKE WITH EPSTEIN PROJECT ON HOLD |
| 01/28/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE - NO ACTIVITY AT THIS TIME. LOT HAS BEEN GRADED BUT NOT STABILIZED |
| 12/29/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. No activity on the site at this time. The site has been rough graded. Temporary fencing remains around half of the cleared area. |
| 09/29/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. No activity at this time
|
| 09/22/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. There is no activity on site at this time. perimeter fencing in place. |
| 06/17/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. No activity on the site. Site has been surveyed and rough graded. Temporary fence remains in place. There are no stormwater controls installed
|
| 06/11/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Unable to locate contact information for contracto |
| 06/11/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Unable to locate contact information for contractor
|
| 08/18/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Still no activity at this time. Temporary fencing for a portion of the property only still in place. |
| 03/12/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued. FOR 2427 N FORGEUS AV Mike with Epstein construction. Looking for electrical and structural inspections for light poles and claims to have no building permit for that work. I referred him to Dave Roberts and Bruce Stevens. |
| 01/28/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE FOR 2427 N FORGEUS AV NO ACTIVITY ON SITE AT THIS TIME |
| 11/05/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by PAHUMAD1 - Continued. Rough grading has been completed |
| 05/18/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - No one on site. Temporary fencing in place. |
| 03/12/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by SFLORES2 - Contractor has demolished the block wall and started rough grading. The site is secured with caution tape. There’s a large pile of dirt with no controls provided. |
| 03/12/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by SFLORES2 - Contractor has demolished the block wall and started rough grading. The site is secured with caution tape. There’s a large pile of dirt with no controls provided. |
| 03/12/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by SFLORES2 - Contractor has demolished the block wall and started rough grading. The site is secured with caution tape. There’s a large pile of dirt with no controls provided. |
| 06/09/2023 |
ENGR Grading Final |
|
Not Ready |
Complete all the work as shown on the approved plans prior to calling in for this final inspection |
| 06/28/2023 |
ENGR Grading Final |
|
Partial Pass |
Trash enclosure footing OK. |
| 07/12/2023 |
ENGR Grading Final |
|
Partial Pass |
|
| 07/26/2023 |
ENGR Grading Final |
|
Partial Pass |
Trash enclosure |
| 08/08/2023 |
ENGR Grading Final |
|
Partial Pass |
Contractor, preparing for asphalt installation |
| 08/16/2023 |
ENGR Grading Final |
|
Passed |
|