Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP19-0166
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
04/22/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - trash closures and rebar inspections necessary for this project. |
04/14/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Trash enclosure pre-grout. Video inspection with Chris. |
04/01/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by SFLORES2 - Trash enclosure footings by video inspection with Chris. |
05/21/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Building number five has been completed. |
05/19/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - Enter not ready for all inspections. This DP is part of a larger development. |
05/20/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - not ready. Complete the drainage swale’s from the rain leader to the curb cut as shown. |
05/19/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Contractor is still working on entry, temporary fencing is still in place. Drainage work as shown on dp still has not yet been installed through landscaped area behind building |
05/12/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Note 15 on page 3 does specify depressed landscaped area behind Cons |
05/12/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Note 15 on page 3 does specify depressed landscaped area behind Michael’s. |
05/11/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - not ready. Provide water harvesting as shown on your city approved Grading and landscape and water harvesting plan. Kris with Epstein, please provide pictures of your civil drawings via text and or email. Thank you |
05/11/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - not ready. Provide water harvesting as shown on your city approved Grading and landscape and water harvesting plan. Kris with Epstein, please provide pictures of your civil drawings via text and or email. Thank you |
04/28/2020 | ENGR Grading Final | TVALENCIA | Continued | Entered by RSALDAT1 - |
04/28/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Contractor preparing for asphalt. Chris via messenger. |
04/22/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Installing curbs. Chris at 481-4745. |
04/10/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - |
04/08/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Pictures via message. Curbs have been installed, trashing closure is in progress. No landscaping has been installed at this time. Contractor is preparing for concrete at front entryway. |
04/08/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Pictures via message. Curbs have been installed, trashing closure is in progress. No landscaping has been installed at this time. Contractor is preparing for concrete at front entryway. |
08/16/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Site grading has just started. |
05/21/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Marshals, building number five is complete. Complete all work shown for this entire development package, stabilize undeveloped lots, and terminate SWPPP for final approval of this permit. |
05/19/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - Enter not ready for all inspections. This DP is part of a larger development. |
05/11/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Work is still ongoing. CERTIFICATION OF CONFORMANCE SPECIFIED FOR FINAL APPROVAL |
07/12/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. No new activity on site at this time. Vacant lots remain. 3730 W River Rd, |
06/04/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - Continued FOR 3730 W RIVER RD. All of the buildings for this site have not yet been built. Permit has expired. |
05/25/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by VLEON1 - CONTINUE FOR 6080 N THORNYDALE RD NO ACTIVITY AT THIS TIME |
06/03/2020 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by RSALDAT1 - No activity on the site at this time. Two of the five buildings have been built. The undeveloped portion has been stabilized with gravel. |
05/11/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - |
08/16/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Desert earth has started grading site. Jobsite shuts down at 1:30. |