Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: DP19-0164

Parcel: 13608032A


Addresses:

2200 S HOUGHTON RD

Inspection Status: Complete (Recurring)

Inspection History: SITE - Stormwater Setup and Controls

Date Description Inspector Results Comments
01/31/2022 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by NGARCIA3 - CN /INSTALLING 15 RCP ON THE NORTH END OF THE BUILDING 2 RUNS 40LF. EACH.
01/26/2022 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VVERA1 - CN/ GOOD AS OF TODAY
10/07/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by RSALDAT1 - CN /GOOD AT IS TIME
08/25/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by NGARCIA3 - ) CN FORMING CATCH BASIN A1 THE REBAR IS SITTING ON THE STORM DRAIN PIPE NEED TO MOVE IT UP 11/2TO 2 INCHES UP .JAMES WILL TAKE A PHOTO AND SEND TO ME WHEN COMPLETED.
07/29/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by RSALDAT1 - CN /POURING ONE HEADWALL AND. CATCH BASIN NORTHWEST OF THE SITE.
07/22/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by RSALDAT1 - CN /TWO CATCH BASIN ARE TO WET TO POUR TODAY. THE CATCH BASIN ARE AT THE NORTHWEST OF SITE.
07/02/2021 SITE - Stormwater Setup and Controls DROBERTS Continued Entered by VLEON1 - CONTINUED, NO CONCERNS DURING THIS INSPECTION
06/28/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN /POURING TWO CATCH BASIN ON THE NORTHWEST OF THE BUILDING.
06/25/2021 SITE - Stormwater Setup and Controls DROBERTS Continued Entered by VLEON1 - CONTINUED AT THIS TIME, NO CONCERNS NOTED DURING THIS INSPECTION.
06/23/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN / INSTALLING 10 STORM DRAIN PIPE
06/15/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN/ FORMED THREE CATCH BASIN AND ONE HEADWALL,SOME STORM DRAINAGE PIPE.
05/27/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN /PUSH BACK THE POUR FOR THE CATCH BASIN FOR TOMORROW.
05/26/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN TWO CATCH BASIN ARE TO POUR.
05/25/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN NEED TO ADDRESS THE ELEVATION AT THE WEST END OF THE MAI BUILDING.FOR DRAINAGE.
05/24/2021 SITE - Stormwater Setup and Controls DROBERTS Partial Approval Entered by VLEON1 - PARTIAL, THIS INSPECTIONS IS NOT REQUIRED AT THIS TIME TIL ADDITIONAL MATERIALS HAVE BEEN INSTALLED. 09154 (STORMWATER FOLLOW-UP) NO CONCERNS AT THIS TIME DURING THIS INSPECTION.
05/22/2021 SITE - Stormwater Setup and Controls DROBERTS Continued Entered by DROBERT5 - THIS INSPECTION IS NOT REQUIRED AT THIS TIME, SCHEDULE THIS INSPECTION WHEN ANY OG THE CONTROLS HAVE BEEN CHANGED OR ADDED. IN THE FUTURE SCHEDULE 09154 STORMWATER FOLLOW UP EVERY 2 WEEKS.
05/19/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - 24” STORM DRAIN PIPE BACKFILLING.
05/18/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - NSTALL OF CONTROLS .10” SOUTH OF BUILDING TWO
05/17/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN / INSTALLING 24” STORM DRAIN PIPE ON THE NORTH EAST END OF PROJECT.
05/13/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN / INSTALLING 36”,30” and 24” STORM DRAIN PIPE THE NORTH OF THE MAIN BUILDING AND THREE HEADWALL SOUTH OF THE MAIN BUILDING.
05/11/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CONTINUE 10 INCH STORM DRAIN
04/21/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN INSPECTED FOUR CATCH BASIN .POUR TOMORROW.
04/16/2021 SITE - Stormwater Setup and Controls DROBERTS Continued Entered by VLEON1 -
03/31/2021 SITE - Stormwater Setup and Controls DROBERTS Continued Entered by RSALDAT1 - 2200 CN CATCH. AND 36” STORM DRAIN
03/10/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CN. INSTALL THE STORMWATER LINE ON THE WEST OF THE BUILDING UNDER THE FIRE LINE RUN.
03/08/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 -
02/23/2021 SITE - Stormwater Setup and Controls MHERNANDEZ Continued Entered by VLEON1 - CONTINUE INSTALLING STORMWATER PIPE 15 INCH