Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
Permit Number - DP19-0129
Inspection Description - PDSD Site/Engineering Division - Landscaping
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/26/2021 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Approved | Entered by RSALDAT1 - APPROVED |
| 02/24/2021 | PDSD Site/Engineering Division - Landscaping | MHERNANDEZ | Cancelled | Entered by VLEON1 - RESCHEDULED FOR TOMORROW |
| 07/09/2021 | PDSD Site/Engineering Division - Landscaping | MHERNANDEZ | Approved | Entered by RSALDAT1 - APPROVED |
| 07/08/2021 | PDSD Site/Engineering Division - Landscaping | MHERNANDEZ | Partial Approval | Entered by RSALDAT1 - PARTIAL NEED TO REPLACE TWO PLANTS ON THE WEST SIDE OF BUILDING AND TWO TREE STAKES AT THE SOUTHEAST OF THE PROJECT. |
| 03/26/2021 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Partial Approval | Entered by VLEON1 - PARTIAL AT THIS TIME THE CONTRACTOR HAS MADE PROGRESS ON THE PREVIOUS NOTES OF ITEMS REMAINING: 1) THEY HAVE PLANS SUBMITTED TO CHANGE THE HANDICAP PARKING SPACES (6) FROM THEIR CURRENT TO A BETTER SPACE SOUTH OF THE MAIN ENTRANCE TO THE SITE. THEY HAVE ADVISED ME THAT THE PLANS ARE APPROVED BY THE REVIEWERS AS WE SPEAK, BUT THEY ARE UNABLE TO PRODUCE A SIGNED COPY OF THE PLANS. 2) THEY HAVE COMPLETED THE MINOR WORK ON THE ROCK RIP RAP PLACEMENT WITHIN THE DRAINAGE LOCATED AT THE NORTHWEST CORNER OF THE SOUTHERN PARKING LOT. 3) THE DRAINAGE WAY ALONG THE SOUTHERN BOUNDARY OF THIS SITE HAS BEEN REPAIRED SO THE WATER WILL FREELY DRAIN FROM THE EAST SIDE OF THE SITE TO THE WEST. 4) THE INSTALLATION OF THE PLANTS, TREES, AND THE PLACEMENT OF THE DECOMPOSED GRANITE HAS BEEN COMPLETED THROUGHOUT THE SITE IN THE MEDIAN ISLANDS. THIS WORK WILL BE FULLY CHECKED ON MY NEXT VISIT TO THIS SITE NEXT WEEK POSSIBLY ON TUES |
| 02/26/2021 | PDSD Site/Engineering Division - Landscaping | DROBERTS | Continued | Entered by RSALDAT1 - CONTINUED, COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS. |
| 02/24/2021 | PDSD Site/Engineering Division - Landscaping | MHERNANDEZ | Cancelled | Entered by VLEON1 - RESCHEDULED FOR TOMORROW |
| 12/09/2020 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Continued | Entered by PAHUMAD1 - Continued. Grading for center parking area. Ramp construction in progress. Garret with MW Morrissey |