Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 07/06/2020 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approved |
| 06/18/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. I spoke with Henry the contractor at 315-447-6323 and requested that he contacted Steve or Alex about his development package permit which is in the approved status but the plans are still under review. I was not able to open the plans and I’m not sure of the scope of the work however Henry said that the job has been finished.
|
| 06/17/2020 |
ENGR Grading Final |
BBENEDONNE |
Continued |
Entered by RSALDAT1 - Continued. It appears as though the work has been completed although there is no inspection history in Pro, Plans in review at this time.
Also CT19CM03476.
Contractor Jack at 6090798
|