Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 12/23/2020 |
ENGR Engineering Final
|
BBENEDON |
Approved |
Entered by RSALDAT1 - Approved |
| 11/20/2020 |
ENGR Engineering Final
|
BBENEDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved. Majority of the asphalt has been installed. Striping in progress. |
| 11/18/2020 |
ENGR Engineering Final
|
BBENEDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved, work in progress. |
| 11/18/2020 |
ENGR Engineering Final
|
BBENEDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved, work in progress. |
| 11/10/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by PAHUMAD1 - Not ready. Please coordinate final inspections with development package 19 Dash 0038. Ray with Ryan companies |
| 12/24/2019 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |