Permit: DP19-0093

Parcel: 132130750


Addresses:

3300 S PARK AV

Inspection Status: Passed

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
03/18/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/23/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Discussion with Dan from Bfl about access requirements for completion of permit. Project estimated completion September
09/23/2019 ENGR Grading Final BBENEDON Approved Entered by VFLORES1 - BFL construction, has started construction, basin has been cut, Temporary fence has been installed.
03/18/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
08/06/2020 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - IS PARTIAL AT THIS TIME, OK FOR TCO AT THIS TIME
08/05/2020 ENGR Grading Final IVR USER Cancelled Entered by IVR USER - IVRS - AP canceled
08/03/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Correct grade at parking Islands for water harvesting.
07/31/2020 ENGR Grading Final IVR USER Cancelled Entered by IVR USER - IVRS - AP canceled
07/02/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Paving and curbs have been installed. No landscaping at this time. Utility work at north east corner.
06/08/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Paving. Dan w/ BFL
06/04/2020 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 -
05/21/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Remote inspection with Dan. Contractor installing final grade and curbs as shown.
05/06/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. 12 inch bleeder pipe on Westbank of basin as shown. Remote inspection with Dan from BFL
05/04/2020 ENGR Grading Final BBENEDON Partial Approval Entered by RSALDAT1 - Contractor preparing for final grade, installing overflow pipe at basin and perimeter fencing. Dan with Bfl
03/26/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Contractor is installing curbs along exterior portion east. And sidewalks near building. Dan Bishop with BFL At 208 Dash 691-9545
12/05/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - No issues or concerns at this time.
11/05/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Builder is preparing for building slab.
11/04/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Contractor on his way offsite at 2:30 PM, requested inspection for the following day.
08/04/2020 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 - . Approved
02/18/2020 ENGR Grading Final DROBERTS Partial Approval Entered by DMERANZ1 - COMPLETE THE TOP ROW OF BLOCK PREPARING THEM FOR THE BOND BEAM AND PROVIDE PHOTOGRAPHS PRIOR TO PLACING GROUT.
01/28/2020 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Block walls to 4 feet.
01/09/2020 ENGR Grading Final DROBERTS Not ready for Inspection Entered by DMERANZ1 - I WILL REINSPECT AT THE END OF THE DAY.Remove the extra dirt around the bollards and provide photos showing the dirt has been removed OK to pour at this time
09/14/2020 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 - Approved