Inspection Status: Not Ready
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
PDSD Engineering Division Pre-Construction SITE |
|
Not Ready |
|
| 01/30/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Track out protection provided. Cut and burn has been provided along the southern portion. Install waddles as required at southwest portion of site. |
| 01/27/2020 |
PDSD Engineering Division Pre-Construction SITE |
DROBERTS |
Approved |
Entered by DMERANZ1 - BORDERLAND CONSTRUCTION IS CURRENTLY WORKING ON CLEARING AND GRUBBING. THEY WILL BE STARTING THE GRADING WORK BY 1/29/2020 IF THE WEATHER COOPERATES. |
| 10/26/2023 |
PDSD Engineering Division Pre-Construction SITE |
|
Partial Pass |
|