Permit: DP19-0083

Parcel: 132130690


Addresses:

3434 S KINO PW

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
04/12/2022 ENGR Grading Final MHERNANDEZ Approved Entered by NGARCIA3 - COMPLETED
05/25/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
09/04/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Site has been graded, there was no activity on the site at this time. No stabilization has been applied to the large area of disturbed dirt as previously requested.
07/13/2020 ENGR Grading Final BBENEDON Continued Entered by JSCHNEI2 - Continued. Final grading
03/23/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - The site has been rough graded, there is a large pile of materials on site. No stabilization has been performed or applied as requested
02/11/2020 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Grading operations are still in progress.
01/27/2020 ENGR Grading Final DROBERTS Partial Approval Entered by DMERANZ1 - BORDERLAND CONSTRUCTION IS CURRENTLY WORKING ON CLEARING AND GRUBBING. THEY WILL BE STARTING THE GRADING WORK BY 1/29/2020 IF THE WEATHER COOPERATES.
02/06/2020 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Rough grading.
10/30/2020 ENGR Grading Final BBENEDON Continued Entered by PAHUMAD1 - Continued. No activity on the side of this time. No stabilization has been applied
09/04/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Site has been graded, there was no activity on the site at this time. No stabilization has been applied to the large area of disturbed dirt as previously requested.
01/30/2020 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Greg with Borderland. Rough grading of open area. Large pile of dirt will be spread out. All materials remain on site. There is no basin. Two-week project. Requested information about plans to stabilize lot after grading has been completed.
12/26/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - NO PLANS
10/26/2023 ENGR Grading Final Not Ready Pending Revision Approval
ENGR Grading Final Requested