Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Engineering Final
|
|
Not Ready |
|
| 10/27/2022 |
ENGR Engineering Final
|
|
Not Ready |
|
| 03/24/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by SFLORES2 - Contractor stockpiling utility piping materials on site. There’s been no stabilization of bare dirt areas.
Borderland is actively providing dust control, water truck on site |
| 03/24/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by SFLORES2 - Contractor stockpiling utility piping materials on site. There’s been no stabilization of bare dirt areas.
Borderland is actively providing dust control, water truck on site |
| 03/24/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by SFLORES2 - Contractor stockpiling utility piping materials on site. There’s been no stabilization of bare dirt areas.
Borderland is actively providing dust control, water truck on site |
| 02/10/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - This was an unscheduled inspection with Boyd from Borderland regarding stabilization of the recently cleared sites that are not currently being developed. |
| 11/04/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by PAHUMAD1 - Not ready. No stabilization has been applied at this time. Water truck is active on site. |