| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 05/13/2022 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, CREWS WORKING ON NEEDED SITE WORK AS NEEDED FOR A FULL C OF O.
6395 E CAMINO BOLEADORAS
|
| 01/21/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN/ NO CHANGE ON SITE AS OF TODAY |
| 10/01/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by NGARCIA3 - CHECK WITH THE CONTRACTOR TO DETERMINE WHAT THE PVC LINES ARE FOR ON THE WEST SIDE OF THE CUL DE SAC BEHIND THE SCUPPERS SOUTH OF LOT #63.
|
| 06/25/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by VLEON1 - CONTINUED AT THIS TIME, CREWS CONTINUE TO WORK MOSTLY IN THE AREA OF ALL ON GOING HOUSES UNDER CONSTRUCTION. THEY ARE ALSO DOING MINOR UTILITY AND SITE WORK AROUND THE NEW HOMES AS NEEDED FOR FUTURE RELEASES, THIS MAY ALSO INCLUDE SIDEWALKS AND DRIVEWAYS.
|
| 05/14/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by RSALDAT1 - CONTINUED. COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS, THIS WILL INCLUDE ALL LOTS, COMMON AREAS, AND DRAINAGE WAYS. ENSURE THAT ALL COMMON AREAS HAVE BEEN HYDROSEEDED WITH A NATIVE PLANT MIX IF DG HAS NOT BEEN PLACED OVER DISTURBED AREAS.
|
| 04/26/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by RSALDAT1 - CONTINUED, VERTICAL WORK ON HOMES AT THIS TIME
|
| 03/04/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by VLEON1 - CONTINUED AT THIS SITE. THE
CLEARING OF THE GRADE FOR VEGETATION IS BEING DONE BY THE CONTRACTOR. PILES OF OLD MATERIAL AND VEGETATION ARE BEING CREATED, THESE WILL EITHER BE REMOVED OR MULCHED AT A LATER DATE. |
| 10/30/2020 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by PAHUMAD1 - GRADING INTERMEDIATE IS CONTINUED AT THIS TIME, CREWS WORKING ON LANDSCAPING ITEMS IN AREAS WHERE THEY WILL BE SEEKING A TCO IN THE FUTURE. ALL OTHER WORK ON THIS SITE MAINLY CONTINUES ONTHE REMAINING STRUCTURES GOING VERTICAL. |
| 10/16/2020 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by JSCHNEI2 - PARTIAL AT THIS TIME, ROADWAYS HAVE BEEN CONSTRUCTED THROUGHOUT, SO LOT RELEASES WILL BE AVAILABLE IN THE NEAR FUTURE. |
| 10/02/2020 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by JSCHNEI2 - CONTINUED AT THIS TIME, CREWS WORKING ON HOME CONSTRUCTION ANS INSTALLATION OF VERTICAL CURB AT THE NORTH WEST CORNER OF THE SITE. |
| 09/18/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue. Working on site walls and houses. |
| 09/04/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by JSCHNEI2 - Continue. Working on houses. |
| 07/10/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. Working on riprap In drainage channels. Working on grading for streets getting ready for paving and sidewalks scuppers. |
| 06/26/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continue. Working on grading roads installing curbs culverts and Street and rip rap and drainage. |
| 05/29/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. Working on grouted riprap in drainage and precast culverts for Rodeway Inn over drainage. Appear to be working on site wall. |
| 05/15/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RSALDAT1 - Continue. Working on grading pads. Working in right away. And in drainage area.
|
| 05/01/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RSALDAT1 - Installing welded wire and grouted riprap in drainage on South east side of s i t e.
|
| 01/10/2020 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Appear to be starting on site utilities site sewer. |
| 12/27/2019 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DMERANZ1 - THE WORK AT THIS TIME CONSIST OF THE CONTRACTOR INSTALLING THE UNDERGROUND UTILITIES. MINOR TRACK OUT NOTED AT THIS TIME THAT WILL NEED TO BE ADDRESSED NEXT WEEK. |
| 12/13/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by SFLORES2 - Working on grading streets. |
| 11/15/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Working on rough grading at this time. |
| 10/18/2019 |
ENGR Grading Final |
RLEDONNE |
Not ready for Inspection |
Entered by DMERANZ1 - Grading work with no controls in place. |
| 08/26/2019 |
ENGR Grading Final |
RLEDONNE |
Not ready for Inspection |
Entered by DMERANZ1 - No activity at this time.
|
| 12/30/2019 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DMERANZ1 - THE FOLLOWING WORK IS BEING DONE AT THIS TIME: GENERAL SITE GRADING FOR THE LOTS AND THE ROADWAYS. THIS SITE NEEDS TO BE CHECKED TOO SEE IF THE CONTRACTOR IS CALLING IN FOR HIS INSPECTIONS. |
| 01/19/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
This part of the subdivision is about 98% completed |
| 01/19/2023 |
ENGR Grading Final |
|
Partial Pass |
This part of the submit subdivision is about 98% completed it |
| 02/03/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Complete all work is shown on the approved plans on this prior to calling him for final inspection |
| 02/03/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Complete I’ll work on this site prior to calling this in for a final inspection |
| 05/04/2023 |
ENGR Grading Final |
|
Not Ready |
Sidewalk inspection needs to be completed prior to finalizing this inspection |
| 08/04/2023 |
ENGR Grading Final |
|
Not Ready |
Complete starting the Vertical Construction on all open lots prior to scheduling this inspection. Also provide this Department with the Notice of Termination Letter from the Arizona Department of Environmental Quality prior to scheduling future Inspections. |
| 08/04/2023 |
ENGR Grading Final |
|
Not Ready |
Complete starting the Vertical Construction on all open lots prior to scheduling this inspection. Also provide this Department with the Notice of Termination Letter from the Arizona Department of Environmental Quality prior to scheduling future Inspections. |
| 10/05/2023 |
ENGR Grading Final |
|
Not Ready |
Three Lots still have not been constructed done so the site cannot be closed at this time. Provide this department, the notice of termination from the Arizona Department of Environmental Quality for this permit if it has been closed out by ADEQ. The sidewalks will have to be poured and completed as shown on the approved plans if this site is needed to be closed for the Development Package. Also, the open lots will have to be covered with 2 inches of decompose granite to close this permit, or the permit will stay open till the houses have been constructed on these three Lot |
| 10/05/2023 |
ENGR Grading Final |
|
Not Ready |
Three Lots still have not been constructed done so the site cannot be closed at this time. Provide this department, the notice of termination from the Arizona Department of Environmental Quality for this permit if it has been closed out by ADEQ. The sidewalks will have to be poured and completed as shown on the approved plans if this site is needed to be closed for the Development Package. Also, the open lots will have to be covered with 2 inches of decompose granite to close this permit, or the permit will stay open till the houses have been constructed on these three Lot |
| 10/27/2023 |
ENGR Grading Final |
|
Not Ready |
Complete this site as shown on the approved plans prior to calling this Inspection in again for another Grading Inspection. |
| 10/27/2023 |
ENGR Grading Final |
|
Not Ready |
Complete this site as shown on the approved plans prior to calling this Inspection in again for another Grading Inspection. |
| 10/28/2022 |
ENGR Grading Final |
|
Partial Pass |
|