Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP19-0030
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/28/2020 | ENGR Engineering Final | RLEDONNE | Approved | Entered by JSCHNEI2 - Approved. |
01/22/2020 | ENGR Engineering Final | RLEDONNE | Partial Approval | Entered by DMERANZ1 - West end of site Only. Complete all revisions before closing out finals. OK for TCO For west end of site only. |
08/27/2019 | ENGR Engineering Final | RLEDONNE | Continued | Entered by DMERANZ1 - Storm water controls have been installed. |
08/28/2020 | ENGR Engineering Final | RLEDONNE | Approved | Entered by JSCHNEI2 - Approved. |
08/24/2020 | ENGR Engineering Final | RLEDONNE | Not ready for Inspection | Entered by JSCHNEI2 - Not ready. Curb ramp from ADA parking over 2% cross slope. Install long-term bicycle parking per approved plan.Complete all signage on site no customers past this point. Complete all work on harvesting areas.Install truncated domes per approved plan. OK for TCO only. Not ready. Curb ramp from ADA parking over 2% cross slope. Install long-term bicycle parking per approved plan.Complete all signage on site no customers past this point. Complete all work on harvesting areas.Install truncated domes per approved plan. OK for TCO only. |