Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP18-0304
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/06/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
12/27/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Pre-grout inspection. |
12/19/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Dumpster footing and bollards. |
06/17/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Work in progress on main office building |
06/04/2020 | ENGR Grading Final | BBENEDON | Approved | Entered by RSALDAT1 - |
06/03/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Waiting for plan revisions for grading. |
02/26/2020 | ENGR Grading Final | DROBERTS | Correction Required | Entered by DROBERT5 - I CONTACTED GENE WITH MW MORRISSEY AND HAVE ADVISED HIM THAT THERE IS ISSUES ON THIS PROJECT WITH THE CMU WALL THAT HAS BEEN CONSTRUCTED ON THE NORTH SIDE OF THE SITE. I ASKED TO MEET WITH HIM AND ANYONE ELSE TO DISCUSS THE ISSUES OF THE CMU WALL THAT HAS BEEN CONSTRUCTED WITHIN THE SITE VISIBILITY TRIANGLE OF THE NORTHERN DRIVEWAY. WE WILL MEET ON SITE TOMORROW MORNING AT 9:00 AM TO DETERMINE WHAT IS THE RESOLUTION FOR THIS PROBLEM. |
12/27/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Courtyard stormwater piping was inspected by building inspector because development package plan had not been approved at time of installation according to Gene. |
12/19/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Gene with Barker Morrissey please call for preconstruction meeting |