Permit: DP18-0302

Parcel: 11006009A

Inspection Status: Passed

Inspection History: ENGR Engineering Final

Permit Number - DP18-0302

Inspection Description - ENGR Engineering Final

Inspection Status - Passed

Date Description Inspector Results Comments
08/12/2020 ENGR Engineering Final Rledonne Approved Entered by RLEDONN1 -
08/28/2020 ENGR Engineering Final RLEDONNE Approved Entered by RSALDAT1 - Approved.
08/26/2020 ENGR Engineering Final RLEDONNE Partial Approval Entered by RSALDAT1 - Partial approval. Work has been completed on project. Provide certification letter from engineer of record that all grading and drainage and trashing closure has been Installed per approved plans For final.
08/25/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by JSCHNEI2 - Not ready. Complete all striping for pedestrian pathway from building one to building two and three. Provide certification letter from engineer of Record for all grading and drainage has been installed per approved plans and for trashing closure construction that was never inspected by the city of Tucson.
08/19/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by JSCHNEI2 - Not ready. Paving and striping contractor canceled.
08/17/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by JSCHNEI2 - Not ready.Asphalt contractor not able to complete work for inspection.
08/06/2020 ENGR Engineering Final RLEDONNE Partial Approval Entered by RSALDAT1 - Partial approval. Pedestrian pathway from building #1 to South side and west side of building number two cross slopes over 2%. Roof drains running over sidewalks and pedestrian pathways on all three buildings. No physical separation on any pedestrian pathways from building one to building two and three and around building three. Provide stabilization and stormwater temporary controls around stock pile on lot west of site. Remove all construction debris. Walked with Dave RobertsAnd contractors around site. And all comments made by Dave Roberts on DP permit and combination permit for building three.
08/05/2020 ENGR Engineering Final RLEDONNE Not ready for Inspection Entered by RSALDAT1 - Not ready. Leave all notes from last inspection. Gate code
07/31/2020 ENGR Engineering Final RLEDONNE Continued Entered by RSALDAT1 - Walk site with new GC went over CERT letter from engineer of record for all grading and drainage. All work was done per approved plans. Provide stabilization and clear or provide permit for stockpile west of site large open area.Remove all construction material from sidewalks to check slopes. Complete all work on approve plan before calling for final grading.
06/04/2020 ENGR Engineering Final RLEDONNE Partial Approval Entered by RSALDAT1 - Partial approval. OK for TCO for building #1 only. Talk to general superintendent he mentioned changes to trashing closure. I told him he needed approval from environmental services. And all changes to approve plans provide COT approved revisions.