Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP18-0298
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/11/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
03/11/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
01/22/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Days excavating has cleared the lot and is preparing rough grade. |
03/11/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
02/11/2021 | ENGR Grading Final | DROBERTS | Continued | Entered by VLEON1 - CONTINUED. I MET AND WALKED THE SITE WITH THE CONTRACTOR AND WALKED THE SITE TO SEE WHAT THEY WILL NEED TO DO TO COMPLETE THIS SITE. MOST OF THE LANDSCAPING HAS BEEN COMPLETED SO I ADVISED THEM THAT THE TREE STAKING NEEDS TO BE DONE ACCORDING TO THE APPROVED PLANS. THEY WERE ALSO WORKING ON THE BASIN AREA POURING THE INLET STRUCTURES, THEY HAVE BEEN ADVISED TO VARIFY THE AREAS WHERE THEY WILL HAVE ROCK RIP RAP PLACED AND IF THE PLANS CALLED OUT FOR MIRAFFI FILTER FABRIC. I ALSO LOOKED AT THE WATER HARVESTING FOR THE SITE AND TOLD THEM THAT THE BASINS SHOULD BE 6 INCHES LOWER THAN THE ADJACENT INLET STRUCTURE TO ENSURE THAT THE QUANTITY IS MET. I ASKED THEM TO SCHEDULE INSPECTIONS OVER THE NEXT 3 WEEKS SO THAT WE CAN MAKE SURE THEY ARE ABLE TO GET A TCO BY THE END OF THIS MONTH. |
02/04/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE PAVING THE PARKING LOT |
01/13/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUED AND LOOKING FOR T.C.O. |
09/30/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by RSALDAT1 - Partially approved. Manhole base |
09/18/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by JSCHNEI2 - Partially approved. 12 inch storm drain as shown on C9. OK to cover. |
09/04/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. Preparations in progress for underground storm water piping. Eric will schedule inspections as needed. |
06/15/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Eric. Waterline will be inspected by building inspection staff. |
05/18/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Building construction in progress. The site work at this time. |
05/14/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Contractor concentrating on building. Has not started any site drainage or trash structures. |
05/01/2020 | ENGR Grading Final | DROBERTS | Continued | Entered by RSALDAT1 - THIS SITE IS GOING VERTICAL AT THIS TIME AND EVERYTHING APPEARS TO BE OK AT THIS TIME, NO REAL SITE CONCERNS. |
04/24/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by RSALDAT1 - Eric is focusing on building erection |
02/06/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractor performing rough grading and is moving materials on an offsite. Is installing office trailer. |
03/11/2021 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
11/04/2020 | ENGR Grading Final | BBENEDON | Continued | Entered by PAHUMAD1 - Continued. Final grading in progress. Curb work in progress |
11/04/2020 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by PAHUMAD1 - Partially approved. Trash enclosure footings |