Inspection Status: Not Ready
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
PDSD Engineering Division Pre-Construction SITE |
|
Not Ready |
|
| 03/02/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Partial Approval |
Entered by VLEON1 - partially approved. Mark with DR Horton. at 730-1781. Site contractor dirt works, SWPPP contractor earthworks. Provide signage, Stormwater controls, and schedule regular inspections for Stormwater and site progress.
|
| 02/25/2021 |
PDSD Engineering Division Pre-Construction SITE |
DROBERTS |
Partial Approval |
Entered by RSALDAT1 - S PARTIAL AT THIS TIME. I MET WITH THE DEVELOPER/CONTRACTR ND DISCUSSED IN DETAIL WHAT WILL BE HAPENNG ON THIS SITE AND OUR CONCERNS.THEY WILL BE CALLING THI INSPECTION IN AGAIN TO MEET WITH US ONCE THEY ARE BEGINNING TO START THE WORK. |
| 06/02/2023 |
PDSD Engineering Division Pre-Construction SITE |
|
Passed |
contractor shall schedule Stormwater follow up inspections as previously requested. |