Permit: DP18-0286

Parcel: 99999999A

Inspection Status: Complete (Recurring)

Inspection History: SITE - Stormwater Setup and Controls

Date Description Inspector Results Comments
03/02/2022 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by VVERA1 - Continued. North and east slopes of pad buildup remain unstabilized minor erosion. Silt fencing along northern portion of site remains in tact
01/27/2022 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by VVERA1 - Continue. SWPPPNOI information obtained and sent to Dave.
08/19/2021 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by NGARCIA3 - Continued. Silt fence installed along north site perimeter.
08/11/2021 SITE - Stormwater Setup and Controls BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. Additional track out rock installed as well as concrete containment
08/05/2021 SITE - Stormwater Setup and Controls BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Track out rock added. Concrete containment provided
07/29/2021 SITE - Stormwater Setup and Controls BBENEDONEZ Denied Entered by RSALDAT1 - Denied. Track out rock is all but gone and needs to be redone.
04/13/2021 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by VLEON1 - Continued. Material expediting in progress. Rough grading. Minor track out noted on Silverbell, protections in place.
03/24/2021 SITE - Stormwater Setup and Controls BBENEDON Partial Approval Entered by RSALDAT1 - Partially approved. Track out protection rock has been installed.
03/02/2021 SITE - Stormwater Setup and Controls BBENEDON Partial Approval Entered by VLEON1 - Partially approved. Some existing Stormwater controls remain at this time. Earthworks contracting will evaluate and provide Stormwater protection as required