Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP18-0277

Parcel: Unknown


Addresses:

3700 S CALLE POLAR


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP18-0277

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
07/15/2020 ENGR Grading Final RLEDONNE Approved Entered by RSALDAT1 - Approved.
07/08/2020 ENGR Grading Final RLEDONNE Partial Approval Entered by RSALDAT1 - Partial approval. Walls for both trash enclosures OK walls only.
06/12/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Rebar in footer for trashing closure on north end of sight OK.
06/08/2020 ENGR Grading Final RLEDONNE Partial Approval Entered by RSALDAT1 - Partial approval. FaceTime Inspection for trash enclosure footer on south end of site. Rebar OK. Footer only.
12/17/2019 ENGR Grading Final RLEDONNE Partial Approval Entered by DMERANZ1 - Rebar for a catch basin at North end of site rebar Installed per approved plan.
10/22/2019 ENGR Grading Final RLEDONNE Partial Approval Entered by KROBLES1 - grading rebar. Partial approval. Notes under other address for same activity number.
09/19/2019 ENGR Grading Final RLEDONNE Continued Entered by PMARTIN1 - Catch basins on south west side of site for complete rebar OK.
09/16/2020 ENGR Grading Final RLEDONNE Approved Entered by JSCHNEI2 - Approved.
06/30/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. No grading activity at this time. Working on landscaping and sidewalks.
06/16/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Met with GC on site he ask about opening up part of the houses we talked about physical separation from construction and the public. Complete sidewalks in that area I’ll check with my smart level. Complete all work in area he wants to open firstAnd get with Armando about opening that area on the building side.
06/05/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. Stop by site got with GC about calling in for inspections work has started on trash Enclosures.
05/27/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - Continue. No grading on site at this time.
11/19/2019 ENGR Grading Final RLEDONNE Continued Entered by DMERANZ1 - Provide revision for outlet pipe at basin on north end of site.
09/06/2019 ENGR Grading Final RLEDONNE Continued Entered by DMERANZ1 - install of 18 inch RCP from most southern catch basin on west side of site to third catch basin.
09/17/2020 ENGR Grading Final rledonne Approved Entered by RLEDONN1 -
09/17/2020 ENGR Grading Final rledonne Approved Entered by RLEDONN1 -
07/29/2020 ENGR Grading Final RLEDONNE Continued Entered by RSALDAT1 - grading check for activity. Walk site with GC went over sidewalks over 2% cross slope‘s. Walk site went over work that needs to be done for finals.