Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP18-0273
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/15/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by DMERANZ1 - |
10/28/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Complete work shown on developing package plan. Depress all landscape areas as shown. Remove construction Debris from site . Plans indicate that all accessible parking spaces are existing. The parking lot has been restriped. Existing spaces are out of compliance. |
07/25/2019 | ENGR Engineering Final | DROBERTS | Not ready for Inspection | Entered by DMERANZ1 - NOT READY AT THIS TIME. |
11/15/2019 | ENGR Engineering Final | BBENEDON | Approved | Entered by DMERANZ1 - |
11/07/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Landscapers are working center court No change to landscape areas in the front |
10/28/2019 | ENGR Engineering Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Complete work shown on developing package plan. Depress all landscape areas as shown. Remove construction Debris from site . Plans indicate that all accessible parking spaces are existing. The parking lot has been restriped. Existing spaces are out of compliance. |