Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Setup and Controls
| Date |
Description |
Inspector |
Results |
Comments |
| 08/03/2021 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by RSALDAT1 - CN |
| 06/24/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Some controls are in place however track out protection is in-adequate. Concrete containment installed. |
| 02/10/2020 |
SITE - Stormwater Setup and Controls |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Concrete containment has been installed some track out protection and some site protection has been installed. Provide more controls as needed. Sweep the streets if any dirt or materials end up offsite. |