Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 06/25/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - continued. Bryan with Desert earth at307-4459
Minor track out noted. Work being done in the right of way. Stormwater protections could use to be contained and strengthened. |
| 04/20/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Builder is doing work within the right of way on all three sides of this site. Contractor is also constructing buildings within the site.
|
| 02/10/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by DMERANZ1 - Construction is underway. Underground sewer piping has been installed and covered. There are material stock piles on site. Please schedule a preconstruction meeting. Superintendent is not on site at this time. Brian at 307-4459 with Miramonte |
| 01/09/2020 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DMERANZ1 - CURRENTLY THE CONTRACTOR IS WORKING ON GENERAL GRADING THROUGHOUT THE SITE FOR LANDSCAPING, AND HAS CONSTRUCTED THE BUILDING SLABS FOR UNITS 1 & 2 AT THIS TIME. |
| 08/21/2019 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - No activity at this time. |
| 08/03/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by RSALDAT1 - CN |
| 05/20/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VLEON1 - |
| 09/09/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. Contractor has north driveway completed and has completed most of the work within the right of way and has removed the street closure barricades. |
| 08/20/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Contractor installing private roadway and curbs and sidewalks in the right of way. |
| 07/23/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Grading, utility work and work within the right of way in progress. Material stock piles on site. |
| 06/01/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Drainage scupper installed Without rebar inspection. Working right away requires right away inspection. |
| 03/12/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by SFLORES2 - There are many piles of material on site. There are two houses under construction at this time utilities have been installed. |