Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP18-0258
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Complete (Recurring)
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/14/2022 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by NGARCIA3 - MINOR SIGNS OF TRACK OUT NOTED ON THE SOUTH SIDE OF THE PROJECT, THE CONTRACTOR WILL BE ADVISED TO CLEAN THE STREETS AS NEEDED. |
05/20/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - |
03/12/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by VLEON1 - CONTINUED, NO CONCERNS AT THIS TIME |
11/10/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by PAHUMAD1 - Continued. Track out at South entrance. |
09/09/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by JSCHNEI2 - Continued. There is a large amount of trackout on Meyer and on Kennedy. Contractor needs to remove all dirt from public streets. |
08/20/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Large dirt ramp in roadway is unacceptable. All dirt from the roadway needs to be removed. Stormwater controls have been mostly rendered in operative and need to be corrected. |
07/23/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. Dirt ramps in two locations, rocks and dirt in the street. Right of way work In progress. |
06/25/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - continued. Bryan with Desert earth at307-4459 Minor track out noted. Work being done in the right of way. Stormwater protections could use to be contained and strengthened. |
06/24/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continued. There is notable track out on all three sides of this site. |
06/01/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - Continue. Track out on all three streets surrounding this project. Note working right away requires right of way permit and inspections. |
04/20/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by RSALDAT1 - There is track out present on Kennedy Street, Meyer Avenue and on Simpson Street. All dirt needs to be removed from the street as soon as possible and at the end of each day. |
03/12/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by SFLORES2 - There is muddy track out on Meyer Street. There is track out protection in one location however contractors are using multiple locations to enter and exit the site. |
02/10/2020 | SITE - Stormwater Follow-up | BBENEDON | Continued | Entered by DMERANZ1 - No issues at this time however more stormwater controls are necessary. |