Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP18-0257
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/16/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CMURPHY1 - |
09/04/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - Trash enclosure slab. |
09/03/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - I spoke with Ryan from MW Morrissey. And Strunk excavating about ensuring that elevation of the overflow at the basin is Installed as shown Reschedule for trash closure slab |
08/19/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Pre-grout for trash enclosure |
07/11/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Install verticals and complete Bond Beam for trash enclosure. |
06/18/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Trash enclosure footing. |
10/01/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
10/15/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by DMERANZ1 - |
10/01/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Contractor still needs to excavate at riprap and curb opening areas. Pony walls and water harvesting and the accessible route from Campbell still have yet to be completed. |
09/04/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - Trash enclosure slab is OK. Contractor is performing final grading and installing underground utilities. |
09/03/2019 | ENGR Grading Final | BBENEDON | Continued | Entered by DMERANZ1 - I spoke with Ryan from MW Morrissey. And Strunk excavating about ensuring that elevation of the overflow at the basin is Installed as shown Reschedule for trash closure slab |
07/11/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by DMERANZ1 - Install verticals and complete Bond Beam for trash enclosure. |
06/18/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by DMERANZ1 - Trash enclosure footing. |
06/10/2019 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by CBELL1 - 18 inch HDPE as shown on plan OK to cover. |
04/16/2019 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by CMURPHY1 - Use this inspection for your below ground drainage piping, grading and walkway installations and your trash enclosure installations. Note trash enclosure shall be installed for city of Tucson detail six-01. With rebar at 32 inches OC vertical. See plans for additional specifications. |