Permit: DP18-0257

Parcel: 13213101A


Addresses:

2975 S KINO PW


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP18-0257

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
04/16/2019 ENGR Grading Final BBENEDON Approved Entered by CMURPHY1 -
09/04/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 - Trash enclosure slab.
09/03/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - I spoke with Ryan from MW Morrissey. And Strunk excavating about ensuring that elevation of the overflow at the basin is Installed as shown Reschedule for trash closure slab
08/19/2019 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Pre-grout for trash enclosure
07/11/2019 ENGR Grading Final BBENEDON Not ready for Inspection Entered by DMERANZ1 - Install verticals and complete Bond Beam for trash enclosure.
06/18/2019 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Trash enclosure footing.
10/01/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 -
10/15/2019 ENGR Grading Final BBENEDON Approved Entered by DMERANZ1 -
10/01/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Contractor still needs to excavate at riprap and curb opening areas. Pony walls and water harvesting and the accessible route from Campbell still have yet to be completed.
09/04/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Trash enclosure slab is OK. Contractor is performing final grading and installing underground utilities.
09/03/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - I spoke with Ryan from MW Morrissey. And Strunk excavating about ensuring that elevation of the overflow at the basin is Installed as shown Reschedule for trash closure slab
07/11/2019 ENGR Grading Final BBENEDON Not ready for Inspection Entered by DMERANZ1 - Install verticals and complete Bond Beam for trash enclosure.
06/18/2019 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - Trash enclosure footing.
06/10/2019 ENGR Grading Final BBENEDON Partial Approval Entered by CBELL1 - 18 inch HDPE as shown on plan OK to cover.
04/16/2019 ENGR Grading Final BBENEDON Not ready for Inspection Entered by CMURPHY1 - Use this inspection for your below ground drainage piping, grading and walkway installations and your trash enclosure installations. Note trash enclosure shall be installed for city of Tucson detail six-01. With rebar at 32 inches OC vertical. See plans for additional specifications.