Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 10/10/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 11/05/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 10/24/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Depress water harvesting areas 6 inches. Install rip rap that head of drainage canal. Provide splash blocks the canopy drains. Insured properly sized trees were installed. Clean spilled over dirt from concrete panel. Install bicycle parking. |
| 10/17/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Complete landscaping, riprap and ground stabilization
Provide notice of termination for the SWPPP from the state. |
| 10/15/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Double stakes all trees removed nursery stakes
|